Oracle Commits to Pay Investors If New Mexico Data Center Lacks Power

MT Newswires Live
2小时前

The Financial Times reports Oracle has promised investors it will continue payments even if a large New Mexico data center fails to secure power before going live.

Insiders say Oracle has issued a force majeure notice to the project's developer, a unit of Blue Owl Capital, over power-supply issues. The project has faced permitting delays amid local opposition. Under contract terms, if the first phase is not ready by a 1H 2027 deadline Oracle must cover a holding-cost payment in lieu of rent for up to three years; one insider said power-delivery risk is borne by Oracle, not investors.

免责声明:投资有风险,本文并非投资建议,以上内容不应被视为任何金融产品的购买或出售要约、建议或邀请,作者或其他用户的任何相关讨论、评论或帖子也不应被视为此类内容。本文仅供一般参考,不考虑您的个人投资目标、财务状况或需求。TTM对信息的准确性和完整性不承担任何责任或保证,投资者应自行研究并在投资前寻求专业建议。