CapitaLand India Trust secures second hyperscaler tenant, lifts pre-leased data-centre capacity to 53%

SGX Filings
01/15

CapitaLand India Trust (CLINT) said on Jan, 15 2026 that it has signed a second long-term agreement with a global hyperscaler to lease Tower 2 of CapitaLand DC Navi Mumbai in Airoli, Navi Mumbai.

With the new contract, CLINT has pre-leased 53% of the total gross power capacity planned for its three data centres under development in Navi Mumbai, Hyderabad and Chennai.

Tower 2 will provide an information-technology load of 37 MW and a gross power capacity of 55 MW. Construction is scheduled to complete in 4Q 2026, with progressive handover to the tenant in 1H 2027.

The agreement follows CLINT’s Dec, 2025 sale of 20.2% stakes in three data centres under development to CapitaLand India Data Centre Fund as part of its capital-recycling strategy. Upon completion of the transaction, expected by Feb, 2026, CLINT will retain a 79.8% interest in the assets while holding rights to participate in up to 33.0% of future India data-centre projects alongside its sponsor, CapitaLand Investment.

As at Jun, 30 2025, CLINT managed assets worth 3.7 billion Singapore dollars, comprising eight IT business parks, three industrial facilities, one logistics park and four data-centre developments across Bangalore, Chennai, Hyderabad, Pune and Mumbai.