CGN's Six Photovoltaic Projects with 1.74 Billion Yuan Total Investment Enter Environmental Review Public Notice

Deep News
09/25

The Pu'er Municipal Ecology and Environment Bureau in Yunnan Province accepted environmental impact assessment documents for six construction projects, including the Daigela Village tea-photovoltaic complementary power generation project, and issued a public notice on the acceptance status on September 21.

According to the notice, these six photovoltaic projects are located in Pu'er City, Yunnan Province, with a combined total investment of 1.74 billion yuan.

Daigela Village Tea-Photovoltaic Complementary Power Generation Project

The project is developed by CGN New Energy (Pu'er) Co., Ltd., with a total investment of 160 million yuan and a construction period of 12 months. The project has a rated capacity of 40MW (AC side) and an installed capacity of 53.71MWp (DC side), with a system capacity-to-load ratio of 1.3422.

Mengma Tea-Photovoltaic Complementary Power Generation Project

The project is developed by CGN New Energy (Pu'er) Co., Ltd., with a total investment of 440 million yuan and a construction period of 15 months. The project plans a rated capacity of 100MW (AC side) and a DC-side installed capacity of 130.1068MWp.

Xinzhai Tea-Photovoltaic Complementary Power Generation Project (Phase II)

The project is developed by CGN New Energy (Pu'er) Co., Ltd., with a total investment of 546 million yuan and a construction period of 12 months. The project plans a rated capacity of 140MW, with a battery module installed capacity of 188.31MWp and a system capacity-to-load ratio of 1.34.

Mangxin Tea-Photovoltaic Complementary Power Generation Project

The project is developed by CGN New Energy (Menglian) Co., Ltd., with a total investment of 88 million yuan and a construction period of 15 months. The project plans a rated capacity of 20MW (AC side) and a DC-side installed capacity of 26.2601MWp.

Banshun Tea Factory Tea-Photovoltaic Complementary Power Generation Project

The project is developed by CGN New Energy (Menglian) Co., Ltd., with a total investment of 220 million yuan and a construction period of 15 months. The project plans a rated capacity of 50MW (AC side) and a DC-side installed capacity of 65.0534MWp.

Hong'an Photovoltaic Power Generation Project

The project is developed by CGN New Energy (Menglian) Co., Ltd., with a total investment of 286 million yuan and a construction period of 15 months. The project plans a rated capacity of 65MW (AC side) and a DC-side installed capacity of 84.7484MWp.

免责声明:投资有风险,本文并非投资建议,以上内容不应被视为任何金融产品的购买或出售要约、建议或邀请,作者或其他用户的任何相关讨论、评论或帖子也不应被视为此类内容。本文仅供一般参考,不考虑您的个人投资目标、财务状况或需求。TTM对信息的准确性和完整性不承担任何责任或保证,投资者应自行研究并在投资前寻求专业建议。

热议股票

  1. 1
     
     
     
     
  2. 2
     
     
     
     
  3. 3
     
     
     
     
  4. 4
     
     
     
     
  5. 5
     
     
     
     
  6. 6
     
     
     
     
  7. 7
     
     
     
     
  8. 8
     
     
     
     
  9. 9
     
     
     
     
  10. 10