The capacity roadmap revealed by Alibaba Cloud at the Computing Conference signals a massive industry transformation.
Alibaba CEO Eddie Wu's statements at the conference sent highly positive signals. Wu disclosed that model token usage doubles every two to three months, demonstrating explosive growth in AI demand.
He also indicated that the company plans additional investments beyond the previously announced 380 billion RMB three-year investment plan to further strengthen computing infrastructure. Wu projected that by 2032, Alibaba Cloud's global data center power consumption will increase tenfold compared to 2022 levels.
On September 24, Morgan Stanley released a research report projecting that Alibaba Cloud will add over 3 gigawatts of new data center capacity annually from 2026 to 2032, nearly equivalent to the total new capacity additions for the entire Chinese market in 2025. This development will provide sustained and robust growth momentum for infrastructure suppliers including data center operators.
UBS Group believes Alibaba Cloud's investment intensity and sustainability guidance "exceeded market expectations." The firm estimates that Alibaba Cloud may expand its data center capacity at a rate of 1-2 gigawatts (GW) annually, potentially translating to incremental capital investments of 100-200 billion RMB per year.
Ten-Year Roadmap: Adding a "Chinese Market" Annually
Morgan Stanley stated that global data center power consumption is expected to reach ten times 2022 levels by 2033, providing macro-level support for cloud providers' large-scale expansion.
The Morgan Stanley report detailed Alibaba Cloud's expansion pathway: starting from approximately 2.5 GW capacity in 2022, reaching the 25 GW target in ten years means investment intensity will remain elevated for the foreseeable future. The firm projects Alibaba Cloud's capacity will reach approximately 5 GW by 2026, with annual additions exceeding 3 GW from 2026 to 2032.
Morgan Stanley noted this means during the seven years from 2026 to 2032, Alibaba Cloud will need to add over 3 GW of capacity annually, a scale "nearly equivalent to our projected 3-4 GW of new capacity additions for the entire Chinese market in 2025."
This indicates that Alibaba Cloud's capital expenditure alone could sustain data center industry growth for years to come.
Based on this analysis, Morgan Stanley maintains a positive outlook on the data center industry, viewing strong token usage growth, increased cloud provider capital expenditure, and surging power demand as direct positives.
The report reaffirmed "Overweight" ratings on data center operators GDS and VNET, positioning them as "key beneficiaries" of Alibaba Cloud's sustained high-intensity investments.
However, the report also highlighted disruptive risks from AI. As AI-native applications gradually become mainstream, the "AI eats software" trend could negatively impact traditional enterprise software companies.
Investment Intensity Exceeds Expectations, Annual Capital Expenditure Increases May Reach Hundreds of Billions
UBS converted Alibaba Cloud's targets into specific capital expenditure estimates in its report. The firm's analyst calculations are as follows:
First, UBS estimates Alibaba Cloud's total data center capacity (IT load) in 2022 was approximately 1.5GW. Using this as baseline, a tenfold increase over ten years would mean total capacity reaching 15GW, representing a net addition of approximately 13GW. This equates to an average annual net addition of at least 1-2GW over the next decade. The report also noted that considering improvements in Power Usage Effectiveness (PUE), actual new capacity requirements could be higher.
Second, UBS linked its capacity growth projections to capital investment. According to the firm's estimates, each 1GW of data center demand, if entirely dedicated to AI, requires approximately 100 billion RMB in IT equipment capital expenditure. Based on this calculation, annual additions of 1-2GW directly correspond to at least 100-200 billion RMB in additional annual capital expenditure.
UBS believes these calculations significantly exceed current market expectations, dispelling market doubts about the sustainability of AI capital expenditure cycles and the investment intensity of hyperscale providers.