COSCO SHIPPING International (Singapore) Co., Ltd. announced that construction works for Jurong Island Logistics Hub Phase II have continued through Mar, 18 2026, with structural works progressing to the third and fourth floors.
Other ongoing activities include internal drainage installation, external driveway construction, fire protection systems and air-conditioning ducting installation. Demolition of parts of the Phase I structure to facilitate its connection with Phase II is proceeding smoothly with minimal disruption to Phase I operations.
The company said it will issue further updates when there are material developments.