COSCO SHIPPING International Reports Progress on Jurong Island Logistics Hub Phase II

SGX Filings
06/12

COSCO SHIPPING International (Singapore) Co., Ltd. announced that construction of Jurong Island Logistics Hub Phase II continued through Jun, 12 2026, with structural works advancing to the sixth and seventh floors of the building.

Additional activities—including superflat floor construction, installation of fire-fighting systems, plumbing, warehouse racking and an overhead crane—are under way to prepare the facility for operations once a Temporary Occupation Permit is obtained.

The company said demolition of the Phase I structure, required for integration with Phase II, has progressed to the seventh level with minimal disruption to current operations.

COSCO SHIPPING International added that it is working closely with main contractor Cogent and other vendors to ensure timely completion and is in discussions regarding a partial Temporary Occupation Permit. Further announcements will follow upon any material developments.

免责声明:投资有风险,本文并非投资建议,以上内容不应被视为任何金融产品的购买或出售要约、建议或邀请,作者或其他用户的任何相关讨论、评论或帖子也不应被视为此类内容。本文仅供一般参考,不考虑您的个人投资目标、财务状况或需求。TTM对信息的准确性和完整性不承担任何责任或保证,投资者应自行研究并在投资前寻求专业建议。

热议股票

  1. 1
     
     
     
     
  2. 2
     
     
     
     
  3. 3
     
     
     
     
  4. 4
     
     
     
     
  5. 5
     
     
     
     
  6. 6
     
     
     
     
  7. 7
     
     
     
     
  8. 8
     
     
     
     
  9. 9
     
     
     
     
  10. 10