Newmark Facilitates $7.1 Billion Financing for Texas AI Data Center

MT Newswires Live
05-23

Newmark Group (NMRK) said Thursday it arranged a $7.1 billion construction loan to support the second phase of an artificial intelligence data center project in Abilene, Texas.

The financing, led by JP Morgan (JPM), will fund part of a $15 billion joint venture among Blue Owl Capital (OWL), Crusoe, and Primary Digital Infrastructure.

The second phase includes the construction of six additional buildings, bringing the total data center campus to eight buildings. Phase one, which began in June 2024, includes two buildings with more than 200 megawatts of capacity and is expected to go live in H1, the company said.

Construction of the second phase began in March 2025 and is expected to deliver 1.2 gigawatts of capacity by mid-2026, Newmark added.

Shares of Newmark Group rose nearly 1% in recent trading activity.

Price: 10.37, Change: +0.09, Percent Change: +0.83

免责声明:投资有风险,本文并非投资建议,以上内容不应被视为任何金融产品的购买或出售要约、建议或邀请,作者或其他用户的任何相关讨论、评论或帖子也不应被视为此类内容。本文仅供一般参考,不考虑您的个人投资目标、财务状况或需求。TTM对信息的准确性和完整性不承担任何责任或保证,投资者应自行研究并在投资前寻求专业建议。

热议股票

  1. 1
     
     
     
     
  2. 2
     
     
     
     
  3. 3
     
     
     
     
  4. 4
     
     
     
     
  5. 5
     
     
     
     
  6. 6
     
     
     
     
  7. 7
     
     
     
     
  8. 8
     
     
     
     
  9. 9
     
     
     
     
  10. 10