BCI Minerals (ASX:BCI) said construction of the first salt component at its Mardie salt and potash project in Western Australia reached over 69% completion as of June 30, and the company is on schedule to meet its target of first salt on ship by the December quarter of 2026, according to a Tuesday filing with the Australian bourse.
The company said 77% of the total pond surface area has been inundated as of June 30, and expects to complete the inundation before the end of the year.