Kinetic Development Group Limited has announced substantial progress in its investment in MC Mining and the ongoing development of the Makhado Project. The company has successfully completed the first to fifth tranches of its share subscription, acquiring 277,557,929 new ordinary shares in MC Mining. Infrastructure works, including power supply, water supply, and road and bridge construction at the Makhado mining area, are advancing as planned, with completion targeted for December 2025. Construction of the mining area infrastructure and coal processing plant is also expected to finish by the end of 2025, with joint commissioning anticipated to begin in January 2026. Kinetic Development Group aims to ultimately hold a 51% stake in MC Mining upon completion of all subscription tranches.