TRX Gold Corporation has announced significant progress on the expansion and upgrade of the processing plant at its Buckreef Gold Project. The company plans to increase plant throughput to more than 3,000 tonnes per day (TPD) over the next 18-24 months, exceeding targets outlined in its recent Preliminary Economic Assessment. The expansion involves major equipment upgrades, including a new pre-leach thickener, flotation plant, ultra-fine grind mill, and a cyanide destruction circuit for improved tailings management. The project will be rolled out in two primary phases, with overall plant upgrades scheduled for completion in fiscal 2026 and the new processing circuits expected by fiscal 2027. TRX Gold is funding the expansion through operational cash flow and available liquidity, while maintaining strong working capital.