BCI Minerals Says Construction Of Western Australia Salt Operation, Potash Project Completed 77% In December 2025 Quarter

MT Newswires Live
01/28

BCI Minerals (ASX:BCI) said that the construction of the Mardie salt operation and potash project in Western Australia reached 77% completion in the December 2025 quarter, according to a Wednesday Australian bourse filing.

It deployed the mine production reporting system and lab information management system as part of the Mardie operating system.

It noted that brine levels for ponds 1 to 9 were in line with operational targets, and it commenced lining of the primary crystallizers during the period.