South32 Reports Delay, Cost Overrun on Taylor Project -- Update

Dow Jones
04/30
 

By Rhiannon Hoyle

 

South32 said the development of the Taylor deposit at its Hermosa project in southern Arizona will take longer and cost more to build than it previously anticipated.

The Australia-based miner said Thursday that work on the project has been slowed by contractor underperformance and productivity challenges, while scope changes, materially higher inflation and U.S. tariffs have contributed to higher costs.

South32 now expects to spend about $3.30 billion building the zinc, lead and silver project near Tucson, compared to an initial estimate of about $2.16 billion. First production is anticipated in the second half of fiscal year 2028, a year later than it estimated before.

"While targeted measures have been implemented to improve shaft construction productivity, our latest assessment has determined that these measures will only partially mitigate the impact of contractor underperformance," Chief Executive Graham Kerr said.

The operation is now expected to reach full capacity in fiscal 2031, instead of fiscal 2030.

Kerr said the project is being challenged by industrywide increases in prices for steel, piping, concrete and other items.

South32 now expects average sustaining capital expenditure requirements around $50 million annually, up from an earlier estimate of about $36 million.

The miner also revised a forecast for average operating unit costs to $100 per metric ton of ore processed. That compared to $86 per ton before, reflecting general inflation and higher assumed energy costs, South32 said.

The company approved the development of the Taylor deposit in 2024, part of a strategy to reshape its portfolio around commodities it views as essential to low-carbon technologies. South32 estimated Taylor could become one of the world's largest, lowest-cost sources of zinc, a metal widely used for galvanizing iron and steel to protect against corrosion.

The Taylor deposit is part of South32's Hermosa project, which includes the Peake copper deposit and the Clark battery-grade manganese deposit.

In its update Thursday, South32 reported an increase in Taylor's ore reserve and mineral resource of 52% and 10%, respectively. It said the mineral resource at Peake had increased by 32%.

South32 now expects an initial operating life at Taylor of roughly 33 years, up from about 28 years before.

 

Write to Rhiannon Hoyle at rhiannon.hoyle@wsj.com

 

(END) Dow Jones Newswires

April 29, 2026 19:31 ET (23:31 GMT)

Copyright (c) 2026 Dow Jones & Company, Inc.

应版权方要求,你需要登录查看该内容

免责声明:投资有风险,本文并非投资建议,以上内容不应被视为任何金融产品的购买或出售要约、建议或邀请,作者或其他用户的任何相关讨论、评论或帖子也不应被视为此类内容。本文仅供一般参考,不考虑您的个人投资目标、财务状况或需求。TTM对信息的准确性和完整性不承担任何责任或保证,投资者应自行研究并在投资前寻求专业建议。

热议股票

  1. 1
     
     
     
     
  2. 2
     
     
     
     
  3. 3
     
     
     
     
  4. 4
     
     
     
     
  5. 5
     
     
     
     
  6. 6
     
     
     
     
  7. 7
     
     
     
     
  8. 8
     
     
     
     
  9. 9
     
     
     
     
  10. 10