Kori Holdings Unit Faces Arbitration Over Subcontract Dispute

MT Newswires
07/06

Kori Holdings (SGX:5VC) revealed that its subsidiary, Kori Construction, received a notice of arbitration from the Singapore International Arbitration Centre, filed by China Railway First Group, on a dispute over a subcontract for the North-South Corridor, which connects Marymount Lane and Pemimpin Place.

China Railway claims SG$3.8 million in project costs. Kori Construction has filed counterclaims worth SG$9.2 million, according to a Friday filing with the Singapore Exchange.

Additionally, China Railway has filed a prima facie objection, challenging the applicability of the arbitration agreement to SG$7.1 million of Kori's counterclaim.

免责声明:投资有风险,本文并非投资建议,以上内容不应被视为任何金融产品的购买或出售要约、建议或邀请,作者或其他用户的任何相关讨论、评论或帖子也不应被视为此类内容。本文仅供一般参考,不考虑您的个人投资目标、财务状况或需求。TTM对信息的准确性和完整性不承担任何责任或保证,投资者应自行研究并在投资前寻求专业建议。

热议股票

  1. 1
     
     
     
     
  2. 2
     
     
     
     
  3. 3
     
     
     
     
  4. 4
     
     
     
     
  5. 5
     
     
     
     
  6. 6
     
     
     
     
  7. 7
     
     
     
     
  8. 8
     
     
     
     
  9. 9
     
     
     
     
  10. 10