Executed $6.6B high-investment grade lease in Sandersville; project is on time, on budget, and fully funded
585 MW in Texas assigned Batch Zero baseload status, setting the stage for continued commercial growth
LAS VEGAS, Nov. 24, 2026 /PRNewswire/ -- CleanSpark, Inc. (Nasdaq: CLSK) ("CleanSpark" or the "Company"), a market leading data center developer, today reported financial and operating results for the fourth quarter and fiscal year ended September 30, 2026.
Fourth Quarter and Fiscal Year Highlights
-- Expanded energy and infrastructure portfolio through strategic
acquisitions of up to 885 MW in Texas, establishing a foundation for
future AI and HPC development
-- Secured 20-year, $6.6 billion triple-net lease at Sandersville with high
investment-grade tenant
-- Fully funded Sandersville development through issuance of 7.875% $2.276
billion senior secured notes due 2031
-- Maintains more than $1 billion in liquidity to support disciplined growth
and infrastructure development
Management Commentary
"Fiscal 2026 was a defining year for CleanSpark as we made significant progress in executing our strategic transformation," said Matt Schultz, Chairman and Chief Executive Officer. "We have spent years building the energy expertise, operational capabilities, and infrastructure portfolio that differentiate our platform today. This year, we demonstrated our ability to translate those strengths into long-term contracted opportunities, while securing the capital necessary to execute. As we look ahead, our focus remains on disciplined execution, strengthening our relationships with the communities and stakeholders critical to our success and creating long-term value for our shareholders."
President and CFO Gary Vecchiarelli commented, "Our financial strategy remains centered on disciplined capital stewardship, maintaining flexibility, and allocating capital to opportunities that deliver the strongest risk-adjusted returns. The completion of our Sandersville financing provides dedicated capital and fully funds the project. Combined with more than $1 billion in liquidity, we believe our financial position provides the flexibility to execute on current projects and selectively pursue future opportunities without compromising our commitment to prudent capital stewardship."
Financial Results:
-- Total revenue of $120.9 million and $576.5 million for the fourth quarter
and full year, respectively, representing year-over-year decreases of 46%
and 25%
-- Net income of $9.8 million or $0.04 per basic share and net loss of
($987.1) million or ($3.74) per basic share for the fourth quarter and
full year, respectively
-- Adjusted EBITDA, a non-GAAP measure reconciled below, of $345.4 million
in the fourth quarter and an adjusted EBITDA loss of ($304.2) million for
the full year
-- Year-end liquidity of approximately $1.3 billion, consisting of
approximately $204.8 million in cash and cash equivalents and
approximately $1,130.5 million in bitcoin holdings, including current and
non-current holdings and bitcoin pledged as collateral
Business and Operational Highlights
AI and HPC Infrastructure Development
Sandersville, GA
-- Secured 20-year, $6.6 billion triple-net lease with high investment grade
tenant
-- Fully funded project development through $2.276 billion issuance of
7.875% senior secured notes due 2031
-- Mitigated exposure to cost overruns by achieving basis of design
alignment on 100% of anticipated project, agreeing to a turnkey, lump sum
development contract with our Engineering, Procurement and Construction
Management general contractor and pre-paying to secure long-lead items
-- Obtained all material building and development permits (zoning, building,
drainage, etc.)
-- Construction progress remains on time and on track to meet first planned
data hall in November 2027
Texas Portfolio
-- Strategic acquisitions of Sealy (285 MW) and Brazoria (up to 600 MW)
assets
-- Secured Conditional Batch Zero Baseload designation on 585 MW (285 MW in
Sealy and 300 MW in Brazoria Phase 1)
-- Received Conditional Batch Zero Studied Load designation for Brazoria
Phase 2 (up to 300 MW)
-- Exclusivity period at Sealy and Brazoria expired during a period of
temporary regulatory uncertainty, commercialization efforts are
proceeding with existing Sandersville tenant and others
-- Received TCEQ permits for Brazoria project
Washington, GA
-- 86 MW of currently energized, grid-connected power
-- Submitted high-density line study to increase power to 500 MW.
Preliminary results indicate ability to support up to 500 MW transmission
capacity over next several years.
-- Acquired 500 acres of adjacent land to support future AI data center
campus
Bitcoin Mining Operations
-- Held 13,530 bitcoin, including collateral, at fiscal year-end, reflecting
a total value of $1.1 billion based on bitcoin prices as of September 30,
2026
-- Mined 7,253 bitcoin in fiscal year 2026, a decrease of 8% year-over-year
despite a 21% decrease in average hashrate to 36.0 EH/s between those
fiscal years
-- Improved fleet efficiency as measured by a fiscal year-end miner
efficiency of 14.8 J/Th compared to 16.7 J/Th at fiscal year-end 2025
-- Generated $30.6 million of derivative-related proceeds in the fiscal year
as a part of the Company's Digital Asset Management program
Investor Conference Call and Webcast
The Company will hold its fiscal Q4 and full year 2026 earnings presentation and business update for investors and analysts today, November 24, 2026, at 4:30 p.m. ET / 1:30 p.m. PT.
Webcast URL: https://clsk.news/fy26update
The webcast will be accessible for at least 30 days on the Company's website and a transcript of the call will be available on the Company's website following the call.
Upcoming Investor Events
CleanSpark is scheduled to participate in Rosenblatt's 2(nd) Annual AI Infra and HPC Conference on Monday, November 30, 2026, the BofA Securities Leverage Finance Conference on Tuesday, December 1, 2026, Chardan's AI Infrastructure Salon on Tuesday, December 1, 2026, the Wells Fargo 10(th) Annual TMT Summit on Tuesday, December 8, 2026 and the 29(th) Annual Needham Growth Conference on Tuesday, January 12, 2027.
If applicable, live presentation webcasts, replay information and updated investor presentations will be available on the Company's investor relations page of its website.
About CleanSpark
CleanSpark (Nasdaq: CLSK), is a market-leading data center developer with a proven track record of success. We control a portfolio of up to 2.1 GW of power, land, and data centers across the United States powered by globally competitive energy prices. Sitting at the intersection of Bitcoin, energy, operational excellence, and capital stewardship, we optimize our infrastructure to deliver superior returns to our shareholders. Monetizing low-cost, high reliability energy by producing a global emerging critical resource -- compute -- positions us to prosper in an ever-changing world.
Forward-Looking Statements
This press release contains forward-looking statements within the meaning of the Private Securities Litigation Reform Act of 1995. In this press release, forward-looking statements include, but may not be limited to, statements regarding the Company's evolving business strategy to expand into the market for data center development, high-performance computing ("HPC"), and artificial intelligence ("AI"), and other statements regarding the Company's expectations, beliefs, plans, intentions, and strategies. In some cases, you can identify forward-looking statements by terms such as "may," "will," "should," "expects," "plans," "anticipates," "could," "intends," "targets," "projects," "contemplates," "believes," "estimates," "forecasts," "predicts," "potential" or "continue" or the negative of these terms or other similar expressions.
The forward-looking statements are subject to a variety of known and unknown risks, uncertainties, and other important factors that may cause our actual results, performance, or achievements to be materially different from any future results, performance, or achievements expressed or implied by the forward-looking statements, including, but not limited to: the success of development and commercialization of some or all of our existing portfolio of bitcoin mining sites, as well as our other power and land assets, as data centers having operations other than bitcoin mining; the Company's ability to identify and acquire new sites and power capacity capable of supporting data centers; risks related to data center construction and operations, including permitting and utility constraints, construction delays, cost overruns, financing and supply-chain challenges, tenant performance, and the possibility that projects may not be completed, delivered or operated on the anticipated timeline, budget or terms; the success of the Company's bitcoin mining activities; the volatile and unpredictable cycles in the emerging and evolving industries in which the Company operates, including the volatility of bitcoin prices; increasing difficulty rates for bitcoin mining; bitcoin halving; changes to compute and data center infrastructure; new or additional governmental regulation, particularly the rapidly evolving federal, state and local regulations impacting data center development in the states in which we operate; dependency on utility rate structures and government incentive programs; dependency on third-party power providers for expansion efforts; the expectations of future revenue growth may not be realized, including in respect of the data center development, leasing, and compute markets; and other risks