CGN POWER (01816) announced that from January to September 2025, the total power generation of nuclear power units operated and managed by the group was approximately 182.822 billion kWh, representing a 2.67% increase compared to the same period last year. Total grid-connected power generation was approximately 172.179 billion kWh, up 3.17% year-on-year.
In the third quarter of 2025, the group completed 4 annual refueling overhauls and 1 first refueling overhaul as scheduled. As of September 30, 2025, the group had completed 12 annual refueling overhauls (including 1 cross-year annual refueling overhaul), 2 ten-year major overhauls, and 1 first refueling overhaul according to plan.
In the fourth quarter of 2025, in addition to continuing the refueling overhauls already underway, the group plans to commence 2 new annual refueling overhauls.
On July 14, 2025, Lufeng Unit 6 achieved dome installation and entered the equipment installation phase. On July 30, 2025, Huizhou Unit 2 completed hot functional testing, laying a solid foundation for the unit's subsequent commercial operation. On September 27, 2025, Cangnan Unit 2 began cold functional testing and entered the commissioning phase.
As of September 30, 2025, the group managed a total of 20 nuclear power units under construction (including 8 units entrusted by the company's controlling shareholder for management), with 4 units in the commissioning phase, 2 units in the equipment installation phase, 3 units in the civil construction phase, and 11 units in the FCD preparation phase.