On-Site Project Tour: Main Construction of Qingdao Hydrogen Energy Industrial Park Hydrogen Refueling Station Project Completed

Deep News
09/28

After more than five months of intensive construction, the main construction of the Qingdao Hydrogen Energy Industrial Park hydrogen refueling station project has recently been completed, with the three individual structures expected to be basically finished in October. The hydrogen refueling canopy at the Qingdao Hydrogen Energy Industrial Park hydrogen refueling station has been approximately 95% completed. Photo by Wang Kai.

At the site, the reporter observed that the hydrogen refueling canopy at the station has been approximately 95% completed, trenches have been dug for the hydrogen island construction, and pipeline laying is currently underway. Li Qizheng, the project construction manager of the hydrogen refueling station, stated that the construction of the three individual structures of the project is expected to be basically completed in October, after which site road construction and outdoor pipeline laying will be accelerated.

The Qingdao Hydrogen Energy Industrial Park hydrogen refueling station project has a total investment of 120 million yuan. The first-phase hydrogen refueling station project commenced construction on April 1, with a planned maximum refueling capacity of 5 tons per day, capable of meeting the refueling needs of 200 hydrogen fuel cell vehicles.

免責聲明:投資有風險,本文並非投資建議,以上內容不應被視為任何金融產品的購買或出售要約、建議或邀請,作者或其他用戶的任何相關討論、評論或帖子也不應被視為此類內容。本文僅供一般參考,不考慮您的個人投資目標、財務狀況或需求。TTM對信息的準確性和完整性不承擔任何責任或保證,投資者應自行研究並在投資前尋求專業建議。

熱議股票

  1. 1
     
     
     
     
  2. 2
     
     
     
     
  3. 3
     
     
     
     
  4. 4
     
     
     
     
  5. 5
     
     
     
     
  6. 6
     
     
     
     
  7. 7
     
     
     
     
  8. 8
     
     
     
     
  9. 9
     
     
     
     
  10. 10