CGN's Six Photovoltaic Projects with 1.74 Billion Yuan Total Investment Enter Environmental Review Public Notice

Deep News
09/25

The Pu'er Municipal Ecology and Environment Bureau in Yunnan Province accepted environmental impact assessment documents for six construction projects, including the Daigela Village tea-photovoltaic complementary power generation project, and issued a public notice on the acceptance status on September 21.

According to the notice, these six photovoltaic projects are located in Pu'er City, Yunnan Province, with a combined total investment of 1.74 billion yuan.

Daigela Village Tea-Photovoltaic Complementary Power Generation Project

The project is developed by CGN New Energy (Pu'er) Co., Ltd., with a total investment of 160 million yuan and a construction period of 12 months. The project has a rated capacity of 40MW (AC side) and an installed capacity of 53.71MWp (DC side), with a system capacity-to-load ratio of 1.3422.

Mengma Tea-Photovoltaic Complementary Power Generation Project

The project is developed by CGN New Energy (Pu'er) Co., Ltd., with a total investment of 440 million yuan and a construction period of 15 months. The project plans a rated capacity of 100MW (AC side) and a DC-side installed capacity of 130.1068MWp.

Xinzhai Tea-Photovoltaic Complementary Power Generation Project (Phase II)

The project is developed by CGN New Energy (Pu'er) Co., Ltd., with a total investment of 546 million yuan and a construction period of 12 months. The project plans a rated capacity of 140MW, with a battery module installed capacity of 188.31MWp and a system capacity-to-load ratio of 1.34.

Mangxin Tea-Photovoltaic Complementary Power Generation Project

The project is developed by CGN New Energy (Menglian) Co., Ltd., with a total investment of 88 million yuan and a construction period of 15 months. The project plans a rated capacity of 20MW (AC side) and a DC-side installed capacity of 26.2601MWp.

Banshun Tea Factory Tea-Photovoltaic Complementary Power Generation Project

The project is developed by CGN New Energy (Menglian) Co., Ltd., with a total investment of 220 million yuan and a construction period of 15 months. The project plans a rated capacity of 50MW (AC side) and a DC-side installed capacity of 65.0534MWp.

Hong'an Photovoltaic Power Generation Project

The project is developed by CGN New Energy (Menglian) Co., Ltd., with a total investment of 286 million yuan and a construction period of 15 months. The project plans a rated capacity of 65MW (AC side) and a DC-side installed capacity of 84.7484MWp.