COSCO SHIPPING International Reports Progress on Jurong Island Logistics Hub Phase II

SGX Filings
06/12

COSCO SHIPPING International (Singapore) Co., Ltd. announced that construction of Jurong Island Logistics Hub Phase II continued through Jun, 12 2026, with structural works advancing to the sixth and seventh floors of the building.

Additional activities—including superflat floor construction, installation of fire-fighting systems, plumbing, warehouse racking and an overhead crane—are under way to prepare the facility for operations once a Temporary Occupation Permit is obtained.

The company said demolition of the Phase I structure, required for integration with Phase II, has progressed to the seventh level with minimal disruption to current operations.

COSCO SHIPPING International added that it is working closely with main contractor Cogent and other vendors to ensure timely completion and is in discussions regarding a partial Temporary Occupation Permit. Further announcements will follow upon any material developments.

免責聲明:投資有風險,本文並非投資建議,以上內容不應被視為任何金融產品的購買或出售要約、建議或邀請,作者或其他用戶的任何相關討論、評論或帖子也不應被視為此類內容。本文僅供一般參考,不考慮您的個人投資目標、財務狀況或需求。TTM對信息的準確性和完整性不承擔任何責任或保證,投資者應自行研究並在投資前尋求專業建議。

熱議股票

  1. 1
     
     
     
     
  2. 2
     
     
     
     
  3. 3
     
     
     
     
  4. 4
     
     
     
     
  5. 5
     
     
     
     
  6. 6
     
     
     
     
  7. 7
     
     
     
     
  8. 8
     
     
     
     
  9. 9
     
     
     
     
  10. 10