Critical Resources (ASX:CRR) to continue “aggressive” exploration at Mavis Lake in 2023

The Market Herald
2023-01-31
  • Critical Resources (CRR) spends roughly $2.6 million on exploration over the December 2022 quarter as it focusses on its flagship Mavis Lake lithium project in Ontario, Canada
  • The company says it ended the quarter with roughly $8.5 million in the bank, which it will largely put towards further exploration and development work at Mavis Lake
  • During the quarter, CRR appointed consultants to begin early-stage metallurgical testwork ahead of a planned mineral resource estimate for the project
  • Meanwhile, over at the Halls Peak project in New South Wales, CRR also signed on an external consultant to kick off resource modelling work
  • Shares in Critical Resources are down 5.17 per cent to 5.5 cents at 2:37 pm AEDT

Critical Resources (CRR) spent just under $2.6 million on exploration over the December 2022 quarter as it focussed on its flagship Mavis Lake lithium project in Ontario.

The company ended the quarter with roughly $8.5 million cash in the bank.

Over the quarter, Critical Resources completed more than 7300 metres of drilling at Mavis Lake, from which it reported multiple assays grading over three per cent lithium.

Thanks to the company’s efforts, the lithium-mineralised Main Zone has been extended by 550 metres to 1300 metres, remaining open.

CRR appointed external consultants to begin early-stage metallurgical testwork and flowsheet development for concentrate production at the project ahead of a planned mineral resource estimate for Mavis Lake.

To help fund its exploration and development work, Critical raised $6.7 million in November. The company said it would put the cash towards its “aggressive” 2023 Mavis Lake drilling program.

Meanwhile, over at the Halls Peak project in New South Wales, CRR has also signed on an external consultant to kick off resource modelling work.

However, the company said the geological “complexities” of the Halls Peak system meant it would require “extended time” to complete preliminary resource modelling.

Shares in Critical Resources were down 5.17 per cent to 5.5 cents at 2:37 pm AEDT.

免責聲明:投資有風險,本文並非投資建議,以上內容不應被視為任何金融產品的購買或出售要約、建議或邀請,作者或其他用戶的任何相關討論、評論或帖子也不應被視為此類內容。本文僅供一般參考,不考慮您的個人投資目標、財務狀況或需求。TTM對信息的準確性和完整性不承擔任何責任或保證,投資者應自行研究並在投資前尋求專業建議。

熱議股票

  1. 1
     
     
     
     
  2. 2
     
     
     
     
  3. 3
     
     
     
     
  4. 4
     
     
     
     
  5. 5
     
     
     
     
  6. 6
     
     
     
     
  7. 7
     
     
     
     
  8. 8
     
     
     
     
  9. 9
     
     
     
     
  10. 10