Hokkaido Electric to Start Construction of New LNG Unit Earlier After Winning Decarbonization Auction

MT Newswires Live
04-29

Hokkaido Electric Power (TYO:9509) has revised the construction and operation timeline for Unit 3 of its Ishikariwan Shinko thermal power station after winning a bid in Japan's second Long-Term Decarbonized Power Resource Auction, according to a Monday filing on the Tokyo Stock Exchange.

Construction of Unit 3 will now start in May 2030 instead of March 2034, with operations beginning in fiscal 2033. Plans for Unit 2 remain unchanged, while Unit 1 has commenced operations in February 2019.

Hokkaido Electric said the adjustment reflects the auction scheme, which aims to support long-term investment in decarbonized power sources.

Price (JPY): $687.30, Change: $+3.5, Percent Change: +0.51%

免責聲明:投資有風險,本文並非投資建議,以上內容不應被視為任何金融產品的購買或出售要約、建議或邀請,作者或其他用戶的任何相關討論、評論或帖子也不應被視為此類內容。本文僅供一般參考,不考慮您的個人投資目標、財務狀況或需求。TTM對信息的準確性和完整性不承擔任何責任或保證,投資者應自行研究並在投資前尋求專業建議。

熱議股票

  1. 1
     
     
     
     
  2. 2
     
     
     
     
  3. 3
     
     
     
     
  4. 4
     
     
     
     
  5. 5
     
     
     
     
  6. 6
     
     
     
     
  7. 7
     
     
     
     
  8. 8
     
     
     
     
  9. 9
     
     
     
     
  10. 10