Bannerman Energy (ASX:BMN) said that the installation of the site water distribution infrastructure was completed at the Etango uranium project in Namibia, according to a Monday Australian bourse filing.
The engineering for the dry processing plant is around 58% complete, per the filing. Meanwhile, detailed engineering on the wet plant is now around 13% complete.
The site access road is around 89% complete, ahead of schedule. A contract for the blasting, crushing, and placement of the drainage layer on the Etango heap leach pads was placed in order to secure costs and supply of the mobile crushing equipment required for the contract.