0907 ET - GE Vernova warns its wind division could be hurt by the Trump administration's efforts to halt offshore wind projects. The wind division recorded higher-than-expected losses during 4Q, CFO Ken Parks says on an analyst call, after the U.S. government in December issued a stop-work order targeting the Vineyard Wind 1 project, located off Martha's Vineyard. A federal judge ruled Tuesday that construction could continue, and if that happens quickly, Parks says the company can complete scheduled work at the site by the end of March. Time is of the essence, though. "At the end of March, we'll lose access to the vessel required to complete installation of the remaining turbines," Parks says. "If we're unable to complete the installation of the remaining 11 turbines, 2026 wind revenue could be negatively impacted by approximately $250 million." (connor.hart@wsj.com)
(END) Dow Jones Newswires
January 28, 2026 09:07 ET (14:07 GMT)