Bannerman Energy Says Bulk Earthworks Contract at Namibia Uranium Project Around 51% Completed

MT Newswires Live
01/29

Bannerman Energy (ASX:BMN) said the bulk earthworks contract at its Etango uranium project in Namibia was around 51% completed during the December 2025 quarter, with major focus remains construction of heap leach pads, according to a Thursday Australian bourse filing.

The company's site contractor workforce for the project increased to over 370 personnel during the December 2025 quarter, with the ramp-up of personnel associated with the civil and aggregate mining, crushing, and screening contracts.

The contract for the installation of the first phase of the permanent water supply pipeline is around 16% completed, the filing said. The engineering, procurement, and construction management consultant for power works is expected to be appointed during the first quarter of 2026.

免責聲明:投資有風險,本文並非投資建議,以上內容不應被視為任何金融產品的購買或出售要約、建議或邀請,作者或其他用戶的任何相關討論、評論或帖子也不應被視為此類內容。本文僅供一般參考,不考慮您的個人投資目標、財務狀況或需求。TTM對信息的準確性和完整性不承擔任何責任或保證,投資者應自行研究並在投資前尋求專業建議。

熱議股票

  1. 1
     
     
     
     
  2. 2
     
     
     
     
  3. 3
     
     
     
     
  4. 4
     
     
     
     
  5. 5
     
     
     
     
  6. 6
     
     
     
     
  7. 7
     
     
     
     
  8. 8
     
     
     
     
  9. 9
     
     
     
     
  10. 10