Alligator Energy Says Completes Commissioning of Samphire Pilot Plant

MT Newswires Live
02/17

Alligator Energy (ASX:AGE) said it has completed both dry and wet commissioning activities at its Samphire Pilot Plant in Australia, in line with the project schedule and within the budget, according to a Tuesday Australian bourse filing.

The company said it will now proceed to energize the plant and undertake final operational preparations with the full operations team recruited and inducted, and final preparation for the field recovery trial (FRT) operations now underway.

The company will start the first test pattern pre-conditioning next week in readiness for uranium extraction, with the FRT to run for about four months, with the first results expected in late March.

Concurrent work streams are progressing, including aggressive drilling programs to commence at Samphire and Big Lake this quarter, the filing added.

免責聲明:投資有風險,本文並非投資建議,以上內容不應被視為任何金融產品的購買或出售要約、建議或邀請,作者或其他用戶的任何相關討論、評論或帖子也不應被視為此類內容。本文僅供一般參考,不考慮您的個人投資目標、財務狀況或需求。TTM對信息的準確性和完整性不承擔任何責任或保證,投資者應自行研究並在投資前尋求專業建議。

熱議股票

  1. 1
     
     
     
     
  2. 2
     
     
     
     
  3. 3
     
     
     
     
  4. 4
     
     
     
     
  5. 5
     
     
     
     
  6. 6
     
     
     
     
  7. 7
     
     
     
     
  8. 8
     
     
     
     
  9. 9
     
     
     
     
  10. 10