Boss Energy (ASX:BOE) lowered its fiscal-year production guidance at its Honeymoon operation in South Australia to between 1.4 million pounds and 1.45 million pounds of triuranium octoxide drummed from the previous guidance of 1.6 million pounds following rainfall in March, according to a Wednesday filing with the Australian bourse.
Despite the downgrade, the company confirmed that it remains on track to deliver fiscal-year C1 cost guidance of AU$36 to AU$40 per pound and an all-in sustaining cost of AU$60 to AU$64 per pound, the filing said.