Brightstar Resources Says Western Australia Gold Project Construction on Schedule

MT Newswires Live
昨天

Brightstar Resources (ASX:BTR) said construction at its Goldfields Project in Western Australia continued to progress through August, and the project remains on schedule for first gold in June 2027, according to a Wednesday filing with the Australian bourse.

Concrete work for the carbon-in-leach circuit is complete, allowing the tank installation team to start on site ahead of schedule, the company said.

It added that the project is tracking within the approved budget, and is expected to deliver average gold production of about 75,000 ounces per year over an initial six-year mine life.

Brightstar continues to evaluate opportunities to enhance and de-risk Goldfields through both organic and inorganic initiatives, with parallel work on mine-life extension opportunities.

免責聲明:投資有風險,本文並非投資建議,以上內容不應被視為任何金融產品的購買或出售要約、建議或邀請,作者或其他用戶的任何相關討論、評論或帖子也不應被視為此類內容。本文僅供一般參考,不考慮您的個人投資目標、財務狀況或需求。TTM對信息的準確性和完整性不承擔任何責任或保證,投資者應自行研究並在投資前尋求專業建議。

熱議股票

  1. 1
     
     
     
     
  2. 2
     
     
     
     
  3. 3
     
     
     
     
  4. 4
     
     
     
     
  5. 5
     
     
     
     
  6. 6
     
     
     
     
  7. 7
     
     
     
     
  8. 8
     
     
     
     
  9. 9
     
     
     
     
  10. 10