Market Chatter: Santos Misses Deadline for First LNG Cargo From Australia Gas Project

MT Newswires Live
昨天

Santos (ASX:STO) missed its 2025-end deadline to ship the first cargo of liquefied natural gas from its AU$6.1 billion Barossa gas project in the Timor Sea, posing an early risk to the oil and gas producer's forecast surge in output in 2026, according to a Wednesday report by the Australian Financial Review, citing a company spokesperson.

Production from the project, originally targeted to commence by June 30, was delayed due to legal and operational challenges, the report added.

According to the report, a Santos spokesperson told AFR that the company took a cautious approach in the final stages of the start-up process while carrying out repairs to piping systems on the offshore vessel.

(Market Chatter news is derived from conversations with market professionals globally. This information is believed to be from reliable sources but may include rumor and speculation. Accuracy is not guaranteed.)

免责声明:投资有风险,本文并非投资建议,以上内容不应被视为任何金融产品的购买或出售要约、建议或邀请,作者或其他用户的任何相关讨论、评论或帖子也不应被视为此类内容。本文仅供一般参考,不考虑您的个人投资目标、财务状况或需求。TTM对信息的准确性和完整性不承担任何责任或保证,投资者应自行研究并在投资前寻求专业建议。

热议股票

  1. 1
     
     
     
     
  2. 2
     
     
     
     
  3. 3
     
     
     
     
  4. 4
     
     
     
     
  5. 5
     
     
     
     
  6. 6
     
     
     
     
  7. 7
     
     
     
     
  8. 8
     
     
     
     
  9. 9
     
     
     
     
  10. 10