According to a report, although the construction process and permitting for large US AI data centers may be significantly delayed after the Democrats won the midterm elections, a recent research report from Wall Street financial giant Goldman Sachs extends its forecast for US data center power capacity to 2028, projecting 52 gigawatts (GW) of new additions that year, nearly three times the increment expected in 2026.
If the 52 GW for 2028 comes online as scheduled, it would set a record for the largest annual increase in US data center power capacity, roughly three times Goldman Sachs' estimated increment for 2026. By comparison, Goldman Sachs expects 18 GW and 28 GW of new additions in 2026 and 2027, respectively, while US data centers added an average of about 4 GW per year from 2021 to 2024 and about 10 GW in 2025.
Just as Goldman Sachs released this research report covering power capacity forecasts, as of the close on November 24 Eastern Time, the global stock market rally in AI computing power and semiconductors triggered by Jensen Huang retaking the helm of Nvidia lasted only one day before experiencing a sharp decline. On Monday, Nvidia surged 31.48%, adding about $952 billion in single-day market capitalization, setting a record for the largest single-day market cap increase for a listed company in the US and globally. On Monday, the strongest capital inflow was still into the AI computing power and semiconductor tech stocks that had previously led the decline and account for the majority of market cap weight—the Nasdaq 100 index rose 6.86%, with constituent companies recovering more than $2 trillion in combined market value. In addition, the Philadelphia Semiconductor Index, which includes chip giants such as Nvidia and AMD, and US-based memory chip giant Micron rose 14.03% and 19.04%, respectively. However, as of Tuesday's US stock market close, the S&P 500 fell 0.50%, the Nasdaq Composite fell 1.48%, and the Philadelphia Semiconductor Index plunged 7.88% to 8,832.50 points, with Micron, AMD, and Nvidia falling 11.01%, 8.86%, and 5.86%, respectively. On Wednesday, selling pressure spread to South Korea and the entire Asian tech stock sector, with the world's two largest memory chip giants Samsung and SK Hynix both falling more than 6% in early trading. South Korea's KOSPI 200 futures dropped 5.12%, triggering the Korean Exchange's sidecar mechanism that suspends program selling orders for five minutes, while the spot market continued trading.
After the US midterm elections, policy changes in Texas, Ohio, and Georgia may slow some large data center projects that have not yet broken ground. In its November 24 research report, Goldman Sachs still firmly extended its power demand expansion forecast to 2028, and after discounting project schedules based on historical delays and cancellations, it expects US data centers to add 52 GW of maximum power capacity that year, close to three times the estimated 18 GW increment for 2026. Of this, approximately 26 GW had not yet started construction at the time the report was published. Whether the 2028 data center power expansion capacity can reach this scale largely depends on whether these projects can be approved, break ground, and be energized on schedule.
Why is the scale of US large AI data center construction accelerating: 18, 28, 52 GW?
Goldman Sachs expects US data center new maximum power capacity to rise from 18 GW in 2026 to 28 GW in 2027, then jump to 52 GW in 2028. The increase in the number of server rooms, the expansion of individual building areas, and the rise in power density per unit area are jointly driving up power supply demand. Of the expected new capacity in 2028, about 35 GW is concentrated in the three major power markets of PJM, Texas ERCOT, and the Midwest MISO, with about 26 GW not yet under construction at the time the report was published. The key to this surge in power capacity is whether, after projects are energized on schedule, the racking of AI server clusters can bring sustained full-load power demand. If the load ramps up as expected, power supply and demand in core regions will tighten further, and gas-fired unit power generation and gas consumption are also expected to increase. This is precisely an important bullish basis for Goldman Sachs' optimistic view on US Henry Hub natural gas prices from 2028 to 2030 and its favor for the data center power equipment chain.
In the view of Goldman Sachs' analyst team, this year's actual increment has already exceeded the baseline levels of previous years. As of the end of October 2026, US data center maximum power capacity increased by 12 GW year-over-year, a gain of 33%. Goldman Sachs estimates this corresponds to an average power demand increase of about 9 GW, more than double the average annual increment of 4 GW from 2022 to 2025. Compared with US Energy Information Administration (EIA) national data through August, data centers contributed more than one-third of the increase in total US power demand. Among the three major regional power markets, PJM, Texas ERCOT, and the Midwest MISO saw capacity increase by 4.4, 2.4, and 2.1 GW year-over-year, respectively. Goldman Sachs expects new capacity of 18, 28, and 52 GW for 2026 to 2028, respectively. It estimates about 10 GW of new additions in 2025, with an average of about 4 GW per year from 2021 to 2024. Goldman Sachs raised its end-2027 capacity from 90 GW to 92 GW, a 44% increase over end-2026. Based on the annual increments in the report, total capacity at end-2028 would be approximately 144 GW. Compared with 2026, the additional approximately 34 GW in 2028 comes from three changes: more newly commissioned buildings, contributing 15.9 GW; higher power density per unit area, contributing 9.5 GW; and larger individual building areas, contributing 9.0 GW. Calculated across all commissioned buildings, average capacity per building increased from 16 MW in 2020 to 31 MW in 2026 and is expected to reach 49 MW in 2028, with the average for newly built buildings even higher. Goldman Sachs expects the average annual growth rates of individual building area and power density to accelerate from about 6% each to 11% and 14%, respectively.
About half of the 52 GW has not yet started construction, where is the commissioning risk concentrated?
The 52 GW is a project forecast after discounting based on historical fulfillment rates. Since May 2026, Goldman Sachs has used Aterio scheduling modeling, incorporating projects already under construction as well as projects that have met key conditions such as financing, permits, grid connection agreements, land, and water rights, then discounting based on historical delays and cancellations. The Goldman Sachs model expects about 60% of scheduled capacity over the next 12 months to achieve commercial operation on time, and about 50% over a two-year period. Using a construction cycle of about two years, most projects scheduled to come online before the third quarter of 2028 have already started construction, and less than half of the capacity scheduled thereafter has reached physical construction milestones. Based on capacity expected to come online under the model, about 5 GW had not yet started construction in 2027, rising to about 26 GW in 2028. This 26 GW is within the 52 GW forecast and directly affects the 2028 fulfillment rate.
Expansion remains concentrated in core power markets. In 2028, Virginia and Texas are expected to contribute a combined 19 GW, about 36%, while PJM, ERCOT, and MISO together contribute 35 GW, about 68%. As shown in the planned projects in the charts below, total unstarted capacity nationwide in 2027 is limited, but the in-state proportions in Florida, Kansas, Tennessee, and Arizona are relatively high. By 2028, unstarted capacity in Texas, Virginia, and Arizona will be approximately 6.4, 3.2, and 2.8 GW, respectively. Risk may further fall on regional power grids. Of the capacity expected to come online in 2028, the proportions not yet under construction in PJM, ERCOT, and MISO are 55%, 45%, and 40%, respectively, while the Southwest Desert, Southeast Georgia, Northwest, and SPP are 68%, 55%, 73%, and 38%, respectively. Goldman Sachs believes that behind-the-meter power, modular delivery, and accelerated construction can improve fulfillment rates. Policy changes after the midterm elections, as well as community resistance in places such as Virginia and Arizona, may increase delays beyond historical discount rates. The charts below track the concentration of new capacity in leading states and regional power grids.
How does 52 GW transmit to the data center power chain, power generation gas, and gas prices?
Goldman Sachs' natural gas baseline originally only included 28 GW of new data center power capacity per year. Its 2027 to 2035 natural gas model assumes that average power load from data centers increases by 18 GW per year, equivalent to about 28 GW of new maximum power capacity per year, consistent with the medium-term estimate of Goldman Sachs' equity research team. The 2027 schedule forecast is close to this baseline, while the 52 GW for 2028 is significantly above the baseline. If projects are energized on schedule and load ramps up as servers come online, regional power supply and demand will tighten further, and there is room for upward revision in power generation gas, supporting Goldman Sachs' bullish judgment on Henry Hub natural gas prices from 2028 to 2030. The charts below compare the two sets of forecasts; the difference in 2025 historical values comes from the data calibers of Aterio versus S&P and Lawrence Berkeley National Laboratory.
Goldman Sachs' overall forecast outlook in this research report partly explains why, even as the AI computing power and semiconductor sector plunges sharply and data center construction expectations are delayed under heavy AI financing costs, power demand forecasts can still be revised upward. The AI computing power and semiconductor theme is repriced almost daily on orders, pricing, and margins, while the fulfillment of power projects is determined by unprecedented urgency for energization, data center construction schedules, grid connection, and equipment commissioning. For investors, the most identifiable progress is project groundbreaking, power supply arrangements being finalized, actual power delivery to server rooms, and load ramping. These milestones determine when the GW in the schedule becomes electricity sales for utilities, as well as actual fuel consumption by gas-fired power plants.
AI training and inference workloads expand power use through different paths. On the training side, larger clusters and more experiments push up accelerator installed scale and operating hours. On the inference side, it depends on call volume, tokens consumed per task, and how many requests servers can handle simultaneously. Long inference and multi-turn agent tasks may repeatedly call models, generate more tokens, and may also reduce concurrency efficiency. Chip upgrades, quantization, and batching can reduce energy consumption per unit of computation. Whether total power use still grows rapidly depends on whether the growth in task volume and computation per task can exceed the decline in energy consumption per unit.
From chips to meters, there are still two conversions: utilization rate and server room losses. The data center supergrid system carries the full-site load of GPUs, CPUs, networking, storage, plus cooling and power distribution losses. Under Goldman Sachs' definition, maximum power capacity is roughly equal to IT equipment power capacity multiplied by power usage effectiveness (PUE). For example, a server room with 100 MW of IT capacity, if average IT load is 80 MW and PUE is 1.2, would have an average full-site load of about 96 MW and annual power consumption of about 0.84 terawatt-hours (TWh). Therefore, 52 GW answers how much power supply capacity needs to be configured. Equipment racking speed, utilization rate, and actual operating hours determine how much electricity is ultimately sold.