The Jinsha River Benzilan Hydropower Station project, the largest hydropower station in the upper reaches of the Jinsha River, has officially commenced construction, marking a significant step in improving the layout of the hydropower base in the upper Jinsha River region.
The station is located in the main stream section of the Jinsha River at the border between Deqin County in Yunnan Province's Diqing Tibetan Autonomous Prefecture and Derong County in Sichuan Province's Garze Tibetan Autonomous Prefecture. It has an installed capacity of 2.6 million kilowatts, equipped with four Francis turbine generator units of 650,000 kilowatts each.
Once completed and operational, the project is expected to generate approximately 10.4 billion kilowatt-hours of electricity annually, saving about 3.47 million tons of standard coal and reducing carbon dioxide emissions by about 8.63 million tons each year.
The Jinsha River Benzilan Hydropower Station is a key project promoted under the national "14th Five-Year Plan" for the modern energy system and renewable energy development. It is the 13th cascade station in the "one reservoir, thirteen cascades" development plan for the upper Jinsha River, spanning both Sichuan and Yunnan provinces, and is the largest hydropower station by installed capacity in the upper Jinsha River.
PowerChina subsidiary Zhongnan Engineering Corporation conducted the full-process survey and design, while the 14th Bureau of Sinohydro is undertaking construction.
The Benzilan Hydropower Station received approval from the National Development and Reform Commission on July 30, 2025. The total installed capacity is 2.6 million kilowatts, using four 650,000-kilowatt Francis turbine generator units, with a designed annual power generation of 10 billion kilowatt-hours. Upon completion, the electricity is planned to be transmitted to Yunnan for consumption. The approved estimated total investment for the project is 34.254 billion yuan.
The feasibility study design sets a total construction period of 10 years, including a 2-year preparatory phase and an 8-year construction phase, with the first unit expected to generate power by 2034.
During the operational period, the project's revenue will come from power generation income. After the station is put into operation, it will participate in the electricity market in accordance with laws and regulations, with the on-grid tariff determined through a competitive mechanism.
Total investment: 34.254 billion yuan. Project legal entity: State Energy Group Jinsha River Benzilan Hydropower Co., Ltd. is the project legal entity for the Benzilan Hydropower Station. It was registered and established in March 2018 in Deqin County, Diqing Prefecture, Yunnan Province, with a registered capital of 4 billion yuan.
Benzilan Company was jointly established by State Energy Investment Group Co., Ltd., Yunnan Provincial Energy Investment Group Co., Ltd., and Sichuan Tietou Kangba Investment Co., Ltd. with contribution ratios of 51%, 34%, and 15%, respectively.
SINA Corp's ESG Rating Center is the industry's first Chinese-language professional ESG information and rating aggregation platform, dedicated to promoting sustainable development, responsible investment, and ESG (environmental, social, and corporate governance) values. It disseminates corporate ESG practices and exemplary efforts, advances China's ESG cause, and promotes the establishment of China's ESG evaluation standards and the improvement of corporate ratings.
Leveraging the ESG Rating Center, SINA Corp has launched multiple ESG innovation indices, providing more options for investors focused on corporate ESG performance. Additionally, SINA Corp has established the China ESG Leaders Organization Forum, working with China's ESG-leading enterprises and partners to promote the establishment of an ESG evaluation standard system suited to China's era through environmental, social, and corporate governance principles, and to advance ESG investment development in China's asset management industry.