Comrades of the Editorial Board: In Luannan County, Hebei Province, a government-invested sewage treatment plant in Huagezhuang Township, built with more than 8 million yuan, has never been put into operation since its completion. Today, crops such as cabbage and corn are being grown in the plant's courtyard. The road surface above the sewage pipeline network has also experienced collapses and other problems. We hope the media will pay attention.
Based on clues provided by a netizen on the "Leadership Message Board," reporters traveled to Luannan County, Tangshan City, Hebei Province, on November 10 to conduct an investigation. Inside the main drainage canal, sewage flows freely and garbage is everywhere; the sewage treatment plant's gate is tightly shut and weeds have overgrown.
When reporters arrived at Huagezhuang Township, the first thing they saw was the black and odorous water body beside the township's main road—the Huagezhuang No. 2 Drainage Main Canal (hereinafter referred to as the "No. 2 Drain"). This central canal running through the Huagezhuang Township area serves flood control and drainage for multiple villages and also performs flood discharge and ecological functions. Reporters observed that the "No. 2 Drain" is overgrown with weeds, piled with domestic garbage, and the water body is pitch-black with white foam floating on the surface, emitting a pungent stench. The black and odorous water body extends more than 3 kilometers from north to south along County Road Guliu Line, with market towns and farmland on both sides, including about several dozen shops and hundreds of farming households.
Following the bank of the "No. 2 Drain" southward, reporters saw four or five drainage outlets on the east side of the canal discharging sewage, with flies swarming around and food residue, plastic foam, plastic bags, wine bottles, and other garbage accumulating near the discharge outlets. Reporters randomly interviewed multiple villagers and shopkeepers, who all expressed considerable resentment about the filth and stench of this main canal.
"When we were children, we used to catch fish and shrimp in the water, and the water quality was good. Later, factories and schools were built, and the canal gradually became polluted. It has gotten worse and worse over the years," said one older villager. "Sewage flows freely all year round. In summer, the stench is unbearable—you can't even open the windows. Now that winter has arrived, it snowed a few days ago, and the smell is a bit less today," said one shopkeeper. "Someone accidentally fell into the water, and the sludge stuck to their body. They washed for a long time and stains still remained. This kind of sludge is extremely stubborn."
About one hundred meters east of the main canal, reporters found the Huagezhuang Township sewage treatment plant mentioned by the netizen. The plant covers a small area, and part of the western fence has collapsed. The iron gate has no signboard and is simply tied with black rope, with no one guarding it. Entering the plant area, weeds are spreading everywhere, with cabbage, corn, and other crops planted in some areas, and agricultural plastic film covering other areas. A equipment room door is locked, and no signs of any machinery operating can be seen. A public notice board hangs outside the equipment room, reading: "Huagezhuang Township, as a provincial-level characteristic town, is required by the higher-level housing and construction department to complete the construction of township-level sewage treatment facilities. In September 2018, approved by the county government, Luannan County Urban Construction Development Co., Ltd. (a subordinate enterprise of the County Housing and Construction Bureau) undertook the construction of this project. The estimated total investment is 8.18 million yuan..."
"The sewage treatment facilities mainly collect production and domestic sewage from the Huagezhuang spinning park, middle school, high school, health center, and street-side shops, benefiting more than 3,000 people in total, with a daily sewage treatment capacity of 500 cubic meters. The sewage pipeline network was laid on Huagezhuang Township Government Avenue, Weili Street, Weiming Street, Nanxin Road, Existing Road, Planned Branch Road, and Weifeng Street, with a total length of 3,062 meters; the sewage treatment plant site is located at the southern end of the Huagezhuang farmers' market, covering about 2.3 mu..."
"When construction started, we were very expectant and happy," said a nearby shopkeeper. But after completion, it was never used. The sewage from shops and villages was never connected to this main network, sewage was still discharged indiscriminately, and the stench and mosquitoes never decreased. Reporters saw on a villager's phone that just a few days earlier, a villager posted a video in the village collective WeChat group complaining that the main canal in front of their door smelled of "pig manure." Others said that because the sewage treatment plant was built, a school was brought in. The sewage treatment plant has never been used, but the school discharges a large amount of sewage, making the "No. 2 Drain" even dirtier.
Guided by villagers, reporters found a drainage pipe outlet with a diameter of more than half a meter on the east side of the canal, discharging dark green sewage. Villagers said: "This is the school's sewage outlet. The school has more than 2,000 teachers and students, and all domestic sewage is discharged here after simple treatment." In subsequent interviews, local authorities stated that the school has its own sewage treatment facilities that meet discharge standards.
Villagers and shopkeepers said they had repeatedly asked relevant departments when the sewage treatment plant would be put into operation, but never received a result. "This sewage treatment plant is just a 'vanity project' and 'image project,'" said one villager.
There are problems of sand leakage and severe blockage, and the sewage pipeline network cannot collect and discharge sewage. Why was the sewage treatment plant built but never used? A villager provided reporters with a statement signed and stamped by the "Luannan County Housing and Urban-Rural Development Bureau" and the "Luannan County Huagezhuang Township People's Government," dated "September 18, 2025." The statement shows: "The project was completed in October 2022. During the commissioning process, it was discovered that the pipeline network and inspection wells from Huagezhuang Yinlong Commercial Building to Changliang Spinning Factory had problems of sand leakage and severe blockage, making the sewage pipeline network unable to collect and discharge sewage. Therefore, the sewage treatment plant was not organized for acceptance inspection and has not yet been put into use. Currently, judicial procedures have been initiated to clarify the responsibilities of the survey, design, construction, and supervision units from a legal perspective. The County People's Court has accepted this case."
In response, Jia Jingshu, Director of the Luannan County Housing and Construction Bureau, confirmed that the Huagezhuang Township sewage treatment plant involves two parts: plant construction and pipeline network construction. Special bond funds of 8 million yuan were secured, with a total investment of 8.87 million yuan, but due to pipeline issues, it has never been put into use.
Not only have the sewage treatment plant and underground pipelines had problems, but the road surface above the pipeline network has also collapsed multiple times in recent years. Walking along the way, reporters could clearly see undulating roads, traces of repairs after collapses, some sewage manhole covers cracked or missing, and some sewage wells filled with sand. "After rain, water often accumulates. We don't dare ride electric bikes, let alone walk through," said one shopkeeper.
On one hand, the sewage treatment plant was built but never used; on the other hand, sewage is directly discharged into the canal. What do local relevant departments think? "Along the 'No. 2 Drain,' there are more than 80 shops and over 1,500 villagers, as well as the township government, schools, health centers, enterprises, etc. It should be said that most of the water discharged into the 'No. 2 Drain' has undergone simple treatment. But we admit that it still qualifies as sewage," said Li Zhinan, Party Secretary of Huagezhuang Township. "It's also possible that some shopkeepers connected sewage pipes to rainwater pipes, allowing untreated sewage to be directly discharged into the canal. Additionally, the Huagezhuang Township market is located along the route, and during market days there is littering, which worsens the pollution."
Construction, design, and survey units pass the buck to each other over project quality issues; legal procedures have been initiated. With more than 8 million yuan invested, how could the sewage treatment plant's project quality be so poor? Who is responsible? Local officials said the construction unit believes it built according to design standards and that the project itself has no problems—it's a design issue; the design unit believes it's a preliminary survey issue, as the survey was based on ordinary rural road load-bearing capacity without considering heavy vehicles passing through.
"The construction party doesn't admit there's a problem, so we brought in a third-party company for appraisal. The expert group identified the main causes of sand leakage as vehicle rolling, concrete sealing rubber ring detachment, and water level differences, and recommended that we take legal procedures to sue the four units involved in survey, design, construction, and supervision," Jia Jingshu introduced.
During the project construction process, did the Housing and Construction Bureau bear regulatory responsibility? Jia Jingshu stated that the administrative department in charge of the Huagezhuang Township sewage treatment plant construction is the Housing and Construction Bureau, and Luannan County Urban Construction Development Company is the contracting unit. The Housing and Construction Bureau should have conducted some supervision, but "during the construction process, the local area was Huagezhuang, and on-site management was the responsibility of Huagezhuang Township. No problems were found."
Some residents reported that the sewage treatment plant was not accepted but all project funds were disbursed, resulting in no one taking responsibility when problems arose. The Housing and Construction Bureau denied this. "Project funds were disbursed according to the contract and project progress. Currently, more than 7.3 million yuan has been disbursed. About 170,000 yuan remains undisbursed for the pipeline network project, which is the quality guarantee deposit. About 1.38 million yuan remains undisbursed for plant equipment installation and infrastructure construction," Jia Jingshu said.
Regarding residents' claims that the sewage treatment plant is a "vanity project" or "image project," the Housing and Construction Bureau disagrees. "From the planning and implementation of this project to its later construction, it was never a 'vanity project,'" Jia Jingshu said. He explained that the County Housing and Construction Bureau had wanted to have the government advance funds to restore the pipeline network and road surface and put the sewage treatment plant into operation while judicial procedures were initiated. "In 2024, the Housing and Construction Bureau asked relevant enterprises to survey and design the pipeline network, formulate a restoration plan, and complete the review, calculating that 2.31 million yuan would be needed. But the legal advisor believed that if restoration were carried out first, it would damage the site and make it impossible to confirm the responsibilities of the four units, so the plan was not implemented."
Currently, local authorities have filed a lawsuit with the court, requesting determination of responsibility and recovery of losses. The court filed the case in 2025 and is conducting testing and appraisal of the project.
Regarding the worsening pollution of the "No. 2 Drain" caused by the sewage treatment plant not being put into use, Li Zhinan stated that daily cleanup work would be increased, including mobilizing enterprises and residents in the jurisdiction to participate in cleanup. A villager told reporters, "This spring, the government organized excavators and took half a month to clean up a large amount of garbage and sludge." But he believes this treats the symptoms, not the root cause.
"Pollution in the 'No. 2 Drain' definitely affects residents' quality of life," Jia Jingshu said. "We consulted environmental protection departments. Before the sewage treatment plant is put into use, the only fundamental solution is interception—transporting sewage and sludge to the sewage treatment plant—but the cost is too high. Only when the sewage treatment plant is operational can this section of sewage be fundamentally treated."
In response, the head of the Luannan County Party Committee stated, "The county must bear responsibility for the pipeline network connection and subsequent operation issues of the Huagezhuang Township sewage treatment plant. The County People's Court will accelerate the trial progress in accordance with laws and regulations. The County Water Conservancy Bureau has proposed a multi-million-yuan dredging project for the 'No. 2 Drain' and is applying for funding. At the same time, using interception treatment methods, sludge will be cleaned through water dilution and chemical treatment."
As of press time, local authorities have begun cleaning up garbage in the "No. 2 Drain" canal. Regarding the activation of the Huagezhuang Township sewage treatment plant, this newspaper will continue to follow up.