American Rare Earths (ASX:ARR) reported positive pre-feasibility study results for its Cowboy State Mine in Wyoming, estimating an after-tax net present value (NPV) of $1.3 billion at an 8% discount rate and an internal rate of return of 24%, according to a late Thursday statement by the company.
The study estimates pre-production capital expenditure, including contingency, at $840 million, highlighting the project's potential to become a major rare earths development in the US, per the statement.
The proposed open-pit mine is expected to operate for 26 years, processing 4.5 million tonnes of material annually and producing an average of around 2,500 tonnes of neodymium-praseodymium (NdPr) oxide each year, the company said.
The company also reported its maiden probable ore reserve of 116.4 million tonnes, containing 1,257 parts per million of payable rare earth oxide.
The company started recovery optimization work with Novex, with every 1% increase in NdPr recovery projected to boost the project's NPV by around $50 million.
The project requires further feasibility assessments, regulatory approvals, financing and processing tests before proceeding to a final development decision, the company said.