For the period from January to September 2026, the nuclear power units managed and operated by CGN Power (01816) generated approximately 189.698 billion kWh of total electricity, an increase of 3.76% compared with the same period last year, the company announced. Total commercial on-grid electricity reached approximately 176.749 billion kWh, up 2.65% year on year.
On August 3, 2026, Huizhou Unit 2 was put into commercial operation. In the third quarter of 2026, the group completed one annual refueling overhaul and one ten-year overhaul as scheduled, and began two new annual refueling overhauls and one ten-year overhaul.
As of September 30, 2026, the group had completed eight annual refueling overhauls, including one that spanned the New Year, and five ten-year overhauls as planned. In the fourth quarter of 2026, in addition to continuing the refueling overhauls already underway, the group plans to launch four new annual refueling overhauls.
On July 31, 2026, Huizhou Units 5 and 6 received approval from the State Council, and as of September 30, 2026, they were in the FCD preparation stage. As of September 30, 2026, the group managed a total of 19 nuclear power units under construction, all from the company's subsidiaries, with two in the commissioning stage, two in the equipment installation stage, eight in the civil construction stage, and seven in the FCD preparation stage.