During the National Day holiday, construction workers on the front lines of various China General Nuclear Power Corporation (CGN) projects were full of passion and drive, playing a song of hard work in their posts and building momentum for the high-quality development of their projects. Multiple projects have refreshed their construction progress bars. Let's take a look together.

Guangdong Taipingling Nuclear Power Project

At present, the second phase of the Guangdong Taipingling Nuclear Power Project is in the civil construction stage. Unit 3 is undergoing fourth-layer shell construction, while Unit 4 is carrying out internal structure base slab foundation construction and other operations, laying a solid foundation for subsequent unit construction. Operations department personnel stayed at their posts, keeping a close eye on the unit operating parameters on the main control screen, carefully checking each indicator and continuously tracking changes in operating conditions.

Zhejiang Sanao Nuclear Power Project

At the construction site of the Zhejiang Sanao Nuclear Power Project, the internal structure pouring of the Unit 3 reactor building has been completed, and all raft foundation steel reinforcement for the Unit 4 reactor building has been tied. Subsequent operations are proceeding in an orderly sequence. Commissioning center personnel moved through every corner of the conventional island, checking every measurement point sign and verifying each pipeline installation section to ensure temperature measurement points are not covered by insulation material.

Guangdong Lufeng Nuclear Power Project

For the Guangdong Lufeng Nuclear Power Project, the main crane in the conventional island of Unit 1 has met availability conditions, Unit 5 has entered the joint commissioning startup stage, and the turbine platform of the Unit 6 conventional island building has completed handover for installation. Construction milestones for each unit are advancing steadily. The nuclear island installation team rooted itself on the front line, checking emergency diesel generator equipment status against procedures without missing a single detail.

Fujian Ningde Nuclear Power Project

Currently, the core engineering milestones of the second phase of the Fujian Ningde Nuclear Power Project are advancing steadily. The 20th layer of the inner containment shell of the Unit 5 reactor building and the 2nd layer of the inner containment shell of the Unit 6 reactor building have both been poured, and construction is moving forward steadily. Employees of the nuclear island installation joint division stayed on the front line of polar crane commissioning, from power-on logic review to load testing, carrying out every process meticulously.

Shandong Zhaoyuan Nuclear Power Project

The first phase of the Shandong Zhaoyuan Nuclear Power Project has entered the peak period of civil construction. The 5th-layer inner shell and 1st-layer outer shell concrete pouring for the Unit 1 reactor building has been completed, and internal wall panel construction is proceeding in an orderly manner. Unit 2 has achieved FCD for the nuclear island, conventional island and cooling tower. Marine engineering and onshore water intake and drainage pipeline construction are in the concrete chain area. Project personnel coordinated production scheduling and emergency response across the sand and gravel plant, mixing station and laboratory, rigorously implemented material acceptance and first-batch pouring witness work, and strictly controlled the concrete production quality gate.

CGN Research Institute Zhongshan Scientific Research Base Project

As one of the important scientific research bases of the China Southern Atomic Energy Science and Technology Innovation Center, the Zhongshan Scientific Research Base has now entered the overall finishing stage. The two laboratory buildings in the base's scientific research plot have been put into use and are intensively carrying out reactor type research and development experiments. The new industry plot is about to complete completion acceptance and enter the final sprint stage, striving toward the goal of high-quality completion and commissioning within the year. At the construction site, safety engineers and safety officers are inspecting the safety status of suspended platforms.

CGN New Energy Tibet Ali Gaize County 50,000-kilowatt Wind Power Project

Currently, all wind turbines of the Ali Gaize County 50,000-kilowatt Wind Power Project have completed hoisting, marking that CGN's highest-altitude wind power project has officially entered the critical stage of grid connection commissioning. The project leader led the team to stay on the front line of the plateau at an altitude of more than 4,600 meters, intensively carrying out equipment commissioning, stabilizing equipment and calibrating parameters.

CGN New Energy Hubei Tuanfeng Weijiachong Pumped Storage Power Station Project

As CGN's first independently developed and constructed pumped storage power station, Unit 1 of the Hubei Tuanfeng Weijiachong Pumped Storage Power Station Project has been successfully connected to the grid and entered trial operation assessment, while Unit 2 is advancing in an orderly manner toward the grid connection target. The project will closely follow the full-capacity commissioning milestone and coordinate the remaining work, defect elimination, project acceptance and production handover. Employees of the pumped storage management center carried out performance testing of the Unit 2 PMU substation at the project's Unit 2 commissioning site.

During the National Day holiday, safety was not relaxed and construction did not stop. CGN people used solid work to strengthen the foundation of energy supply security.

Disclaimer: Investing carries risk. This is not financial advice. The above content should not be regarded as an offer, recommendation, or solicitation on acquiring or disposing of any financial products, any associated discussions, comments, or posts by author or other users should not be considered as such either. It is solely for general information purpose only, which does not consider your own investment objectives, financial situations or needs. TTM assumes no responsibility or warranty for the accuracy and completeness of the information, investors should do their own research and may seek professional advice before investing.