CGN's Six Photovoltaic Projects with 1.74 Billion Yuan Total Investment Enter Environmental Review Public Notice

Deep News
Sep 25

The Pu'er Municipal Ecology and Environment Bureau in Yunnan Province accepted environmental impact assessment documents for six construction projects, including the Daigela Village tea-photovoltaic complementary power generation project, and issued a public notice on the acceptance status on September 21.

According to the notice, these six photovoltaic projects are located in Pu'er City, Yunnan Province, with a combined total investment of 1.74 billion yuan.

Daigela Village Tea-Photovoltaic Complementary Power Generation Project

The project is developed by CGN New Energy (Pu'er) Co., Ltd., with a total investment of 160 million yuan and a construction period of 12 months. The project has a rated capacity of 40MW (AC side) and an installed capacity of 53.71MWp (DC side), with a system capacity-to-load ratio of 1.3422.

Mengma Tea-Photovoltaic Complementary Power Generation Project

The project is developed by CGN New Energy (Pu'er) Co., Ltd., with a total investment of 440 million yuan and a construction period of 15 months. The project plans a rated capacity of 100MW (AC side) and a DC-side installed capacity of 130.1068MWp.

Xinzhai Tea-Photovoltaic Complementary Power Generation Project (Phase II)

The project is developed by CGN New Energy (Pu'er) Co., Ltd., with a total investment of 546 million yuan and a construction period of 12 months. The project plans a rated capacity of 140MW, with a battery module installed capacity of 188.31MWp and a system capacity-to-load ratio of 1.34.

Mangxin Tea-Photovoltaic Complementary Power Generation Project

The project is developed by CGN New Energy (Menglian) Co., Ltd., with a total investment of 88 million yuan and a construction period of 15 months. The project plans a rated capacity of 20MW (AC side) and a DC-side installed capacity of 26.2601MWp.

Banshun Tea Factory Tea-Photovoltaic Complementary Power Generation Project

The project is developed by CGN New Energy (Menglian) Co., Ltd., with a total investment of 220 million yuan and a construction period of 15 months. The project plans a rated capacity of 50MW (AC side) and a DC-side installed capacity of 65.0534MWp.

Hong'an Photovoltaic Power Generation Project

The project is developed by CGN New Energy (Menglian) Co., Ltd., with a total investment of 286 million yuan and a construction period of 15 months. The project plans a rated capacity of 65MW (AC side) and a DC-side installed capacity of 84.7484MWp.

Disclaimer: Investing carries risk. This is not financial advice. The above content should not be regarded as an offer, recommendation, or solicitation on acquiring or disposing of any financial products, any associated discussions, comments, or posts by author or other users should not be considered as such either. It is solely for general information purpose only, which does not consider your own investment objectives, financial situations or needs. TTM assumes no responsibility or warranty for the accuracy and completeness of the information, investors should do their own research and may seek professional advice before investing.