Dec 7 (Reuters) - EDPR :
* ITS SUBSIDIARY EDP RENEWABLES NORTH AMERICA SIGNS WITH CLEVELAND-CLIFFS LONG-TERM COMMERCIAL AGREEMENT FOR THIRD PHASE OF HEADWATERS WIND FARM IN INDIANA (U.S.)
* CONTRACT TO ENABLE CONTINUED DEVELOPMENT AND PLANNED CONSTRUCTION AND OPERATIONS OF 200 MW HEADWATERS III WIND FARM
* 15-YEAR POWER PURCHASE AGREEMENT $(PPA)$EXECUTED FOR 180 MW OF THE 200 MW HEADWATERS III WIND FARM IN RANDOLPH COUNTY
* HEADWATERS III ANTICIPATED TO BE OPERATIONAL IN 2025 AND WILL ANNUALLY POWER EQUIVALENT OF OVER 54,000 AVERAGE INDIANA HOMES
* EDPR NA HAS DEVELOPED AND WILL CONSTRUCT, OWN, AND OPERATE HEADWATERS III WIND FARM
Further company coverage:
(Gdansk Newsroom)
((gdansk.newsroom@thomsonreuters.com; +48 58 769 66 00;))
Disclaimer: Investing carries risk. This is not financial advice. The above content should not be regarded as an offer, recommendation, or solicitation on acquiring or disposing of any financial products, any associated discussions, comments, or posts by author or other users should not be considered as such either. It is solely for general information purpose only, which does not consider your own investment objectives, financial situations or needs. TTM assumes no responsibility or warranty for the accuracy and completeness of the information, investors should do their own research and may seek professional advice before investing.