Release Date: March 14, 2025
For the complete transcript of the earnings call, please refer to the full earnings call transcript.
Q: Can you confirm if the declaration of commercial production is just an accounting declaration or does it apply to your commercial offtake contracts as well? A: It's purely an accounting declaration related to the plant. We've already called commercial production on the LG and Tesla contracts, and we're planning to do that for the Ford contract in July as previously announced. - Antonino Ottaviano, CEO
Q: Have discussions progressed on the potential for new debt capacity with potential lenders to improve liquidity through the underground ramp-up? A: We have the capacity to secure an additional $100 million of Australian debt and are exploring the best options for Liontown. We are in discussions with various groups. - Jon Latto, CFO
Q: Can you explain the increase in the paste plant spend from the original EPC contract estimate? A: The increase reflects the overall cost, including additional components beyond the EPC contract. The project is complete, and commissioning is scheduled for May 14. - Adam Smits, COO
Q: How should we think about depreciation and amortization (D&A) going forward as you work through the open pit? A: We expect D&A to decrease as the open pit is fully amortized. For FY25, it will be slightly less than the first half, with a more significant drop expected from FY27 onwards. - Jon Latto, CFO
Q: What was the catalyst for presenting the capital return strategy now, given current market conditions? A: We want to demonstrate to the market that we are maturing as a company and have a capital allocation strategy in place. This shows our confidence and forward-thinking approach. - Antonino Ottaviano, CEO
Q: If lithium prices remain low, how are you thinking about liquidity and potential additional funding? A: We are monitoring our cash balance and have cost optimization measures in place. We have a $100 million facility option available and are considering other funding options if needed. - Antonino Ottaviano, CEO
Q: When will underground ore be processed through the plant? A: A trial is scheduled for this month, processing about 60,000 tonnes of development ore. This will help with planning for Q4 and CY26. - Adam Smits, COO
Q: How do you expect recoveries to perform with higher underground grades? A: We are focused on ore cleanliness, which is more critical to plant performance than grade. We expect the plant to perform well with higher grades, potentially improving recoveries. - Adam Smits, COO
For the complete transcript of the earnings call, please refer to the full earnings call transcript.
This article first appeared on GuruFocus.Disclaimer: Investing carries risk. This is not financial advice. The above content should not be regarded as an offer, recommendation, or solicitation on acquiring or disposing of any financial products, any associated discussions, comments, or posts by author or other users should not be considered as such either. It is solely for general information purpose only, which does not consider your own investment objectives, financial situations or needs. TTM assumes no responsibility or warranty for the accuracy and completeness of the information, investors should do their own research and may seek professional advice before investing.