港铁(00066.HK) 预期,北环线古洞站月台改造工程所有工序可于今年第四季完成,项目将如期于今年内平顶,预计2027年竣工。
北环线第一期项目执行主管罗廸高透露,团队预计今个月内可完成安装所有往落马洲方向月台的玻璃幕墙,并陆续开始安装往上水方向月台的幕墙,以及两个月台的幕门。
由于安装幕门的位置相当接近行车隧道内的高压电缆,因此港铁指工程团队必须遵从严格指引施工时确保不会对现有铁路设施构成影响,并与车务团队制定不同的应变方案,假设出现影响翌日列车服务的情况,亦希望将影响减低及可尽快进行修复,同时会透过不同渠道尽早通知乘客。(jl/u)(港股报价延迟最少十五分钟。沽空资料截至 2025-07-04 16:25。)
Disclaimer: Investing carries risk. This is not financial advice. The above content should not be regarded as an offer, recommendation, or solicitation on acquiring or disposing of any financial products, any associated discussions, comments, or posts by author or other users should not be considered as such either. It is solely for general information purpose only, which does not consider your own investment objectives, financial situations or needs. TTM assumes no responsibility or warranty for the accuracy and completeness of the information, investors should do their own research and may seek professional advice before investing.