消息称台积电日本 JASM 第二晶圆厂延至 2029 年上半年投运,推迟 18 个月

IT之家
25 Jul

IT之家 7 月 25 日消息,日本媒体《日刊工业新闻》当地时间今日报道称,台积电在日合资子公司 JASM 位于熊本县的第二座晶圆厂项目投运将出现 18 个月的延迟,后移到 2029 年上半年。台积电对 JASM 第二晶圆厂的最初规划是 2024 年内动工、2027 年投产,但动工时间已被调整到 2025 年内。台积电掌门人魏哲家此前表示,JASM 新晶圆厂的延迟与交通有关,但媒体指出更深层的原因...

Source Link

Disclaimer: Investing carries risk. This is not financial advice. The above content should not be regarded as an offer, recommendation, or solicitation on acquiring or disposing of any financial products, any associated discussions, comments, or posts by author or other users should not be considered as such either. It is solely for general information purpose only, which does not consider your own investment objectives, financial situations or needs. TTM assumes no responsibility or warranty for the accuracy and completeness of the information, investors should do their own research and may seek professional advice before investing.