台积电在日本熊本第二座晶圆厂将延至2029年上半年投产

格隆汇
25 Jul

据日媒,台积电在日本熊本县菊阳町兴建的第二座晶圆厂,投产时间将从原订的2027年底延后至2029年上半年。台积电今年稍早曾以当地交通问题为由,预告延后动工,最新规划显示,工程将延迟至2025年下半年启动。目前熊本一厂已于2024年底量产,主要生产12至28纳米制程的车用逻辑芯片与影像传感器。报道指,日本是台积电海外布局的一环,公司此前承诺在美国投资逾千亿美元扩产。此次的延迟反映地缘政治与基础建设挑战,正影响全球半导体供应链重组步调。

Disclaimer: Investing carries risk. This is not financial advice. The above content should not be regarded as an offer, recommendation, or solicitation on acquiring or disposing of any financial products, any associated discussions, comments, or posts by author or other users should not be considered as such either. It is solely for general information purpose only, which does not consider your own investment objectives, financial situations or needs. TTM assumes no responsibility or warranty for the accuracy and completeness of the information, investors should do their own research and may seek professional advice before investing.