Press Release: ALLIED GOLD REPORTS SECOND QUARTER 2025 RESULTS: SOLID PRODUCTION AND PROGRESS ON GROWTH PIPELINE

Dow Jones
Aug 07

TORONTO, Aug. 6, 2025 /PRNewswire/ - Allied Gold Corporation (TSX: AAUC) $(AAUC)$ ("Allied" or the "Company") reports second quarter of 2025 production of 91,017 gold ounces which aligns with plan, represents an increase of 8.3% from last quarter, and positions the Company to meet its guidance for the year as presented below.

SECOND QUARTER HIGHLIGHTS

Operational Highlights

   -- Production, Costs and Guidance: The Company produced 91,017 ounces of 
      gold in the second quarter, in line with plan, positioning the Company to 
      meet its guidance for the year. In the first half of the year, the 
      Company continued implementing improvements to its operations, and 
      undertook a series of operational enhancements and strategic initiatives 
      aimed at delivering a materially stronger going forward, beginning in the 
      second half of the year. These included confirmatory drilling of 
      high-grade areas, continued refinement of block models and grade-control 
      processes, progressive mobilization of new mining equipment at Sadiola 
      for material improvement of fleet availability and productivity, changes 
      to mine management hiring experienced local management including in Mali, 
      and continued advancing stripping at Bonikro and Agbaou to access higher 
      grade ore in the second half of the year and next, with increased 
      operational flexibility. These initiatives provide further confidence to 
      guidance, with production expected on the basis of 55% in the second half 
      of the year by comparison of 45% in the first half of the year. Third 
      quarter production is anticipated to be comparable to the second quarter, 
      while fourth quarter production is expected to be meaningfully higher at 
      118,000 to 122,000 ounces, driven mainly by higher grades. The increase 
      in production in the second half of the year, along with operational 
      improvements and mine sequencing, is expected to drive meaningful cost 
       improvements. 
 
   -- Sales of 81,103 gold ounces. Timing of final shipments resulted in 9,914 
      oz of gold production in Q2 that was sold in July for revenue of $30 
      million that will be recognized in the third quarter. 
 
   -- Total cost of sales(4), cash costs(1) and All-in Sustaining Costs 
      ("AISC")(1) per ounce sold of $2,294, $2,034, and $2,343, respectively 
      (which include royalties based on higher gold prices and the amount for 
      increased waste removal at Agbaou which will result in higher production 
      in H2 and next year). The Company expects costs to be in line with annual 
      guidance taking into account higher gold prices on operating costs with 
      the previously disclosed gold price-based royalties. Second half AISC(1) 
      is anticipated to decrease and be approximately $1,850, based on a $3,000 
      gold price, from the normalization of timing of sales, higher production 
      and the benefit of disproportionate operating and stripping costs in the 
      first half. Further, the ongoing benefits from cost control and reduction 
      programs, the completion and commissioning of Phase 1 along with further 
      upside from potential oxide discoveries at Sadiola which provide 
      relatively inexpensive high-quality ounces, progressive cost improvements 
      quarter-over-quarter are expected. The impact on cash flows is magnified 
      in the fourth quarter, when production is guided to meaningfully 
      increase. 
 
   -- Results for the first half of the year and expectations for the second 
      half of the year are summarized as follows: 
 
                                      Q1 2025                           Q2 2025          Q3 2025            Q4 2025 
-----------  --------------------------------  --------------------------------  ---------------  ----------------- 
Production 
 ounces                                84,040                            91,017  88,000 - 91,000  118,000 - 122,000 
AISC(1)      $                          1,811  $                          2,343              Second half of year at 
                                                                                               approximately $1,850 
-----------  --------------------------------  --------------------------------  ---------------------------------- 
 
   -- Performance by Asset: 
 
          -- At Sadiola, production during the quarter was 49,283 ounces and 
             included continued contributions from the Korali-Sud zone, 
             demonstrating the significant production upside that new oxide 
             orebodies can provide to Sadiola in anticipation of the start of 
             production of the first phase expansion in the fourth quarter. 
 
          -- At Bonikro, production was 25,775 ounces driven by higher grade 
             ore mined from PB3, and improved throughput and recovered grade in 
             the process plant. 
 
          -- At Agbaou, production was 15,959 ounces. Following a plan for 
             longer term optimization and increases in mine life, the Company 
             prioritized waste removal over ore extraction to manage 
             storm-water inflows into the pit and to secure access to 
             higher-grade ore in the second half of 2025 as well as to support 
             increased operational flexibility and production levels in 2026. 
             While waste movement is expected to continue at similar levels for 
             the remainder of the year, ore feed, gold grades and production 
             are expected to materially increase quarter over quarter, 
             resulting in reduced costs and increased cash flows in the second 
             half of the year. Consequently, annual production for Agbaou, and 
             the benefits in the second half of the year, results in a 
             production expectation at the mid-point of guidance of 
             approximately 83,500 ounces. 
 
   -- Expansion of Exploration Success: Due to ongoing exploration successes 
      and proven delivery of results, the Company has committed a further $17 
      million in exploration spending. Of this total $5.7 million is allocated 
      for Sadiola, as the Company believes it can increase inventory 
      meaningfully, including finding new oxide ounces. At Côte d'Ivoire 
      (CDI) an additional $7.5 million has been allocated to pursue 
      opportunities to extend the mine life by increasing Mineral Reserves 
      through sustained drilling and other exploration efforts. At Kurmuk, an 
      additional $3.7 million was added to the exploration budget to support 
      the Company objective of achieving an inventory of 5 million gold ounces. 
      Total year exploration expenditure is now expected to be approximately 
      $37 million. The Company anticipates providing updates for Sadiola in 
      October, Kurmuk in November and CDI in January of 2026. 

Financial Results Highlights

   -- Earnings: 
 
          -- Second quarter net loss of $25.4 million or $(0.22) per share. 
 
          -- Second quarter adjusted earnings(1) of $16.2 million or $0.14 per 
             share. 
 
   -- Cash Flows and EBITDA 
 
          -- Net cash generated from operating activities for the quarter was 
             $22.0 million. 
 
          -- Operating cash flow before income tax paid and movements in 
             working capital was a strong inflow of $116.0 million. 
 
          -- EBITDA(1) and Adjusted EBITDA(1) for the three months ended June 
             30, 2025, were $23.0 million and $71.7 million, respectively. 
 
   -- Strong Financial Position: As of June 30, 2025, the Company had cash and 
      cash equivalents of $218.6 million. The Company has immediately available 
      credit of $50.0 million (inclusive of a $10.0 million accordion) under 
      its revolving credit facility, which remains undrawn. In addition to 
      available credit, the Company has liquidity available through future 
      draws on the Kurmuk gold stream. Available liquidity, coupled with an 
      anticipated step change in production and commensurate cost reduction for 
      the remainder of the year resulting in additional flexibility from 
      increased cash flows, positions the Company to execute on Kurmuk's 
      remaining capital expenditures. 

Advancement of Key Growth Initiatives

Kurmuk: The Company continues to track well against plan for the Kurmuk Project, both in terms of physical completion and spend, having continued to achieve key milestones and progress during the second quarter of 2025. The Company is well-positioned to achieve the goal of commencing production by mid-2026. Being less than a year away from first production, the Company is advancing technical studies aimed at improving operational confidence and flexibility, including potential increases in plant throughput among other improvements and targeted optimizations.

At the end of the second quarter, Engineering and Procurement have achieved approximately 90% progress. Transportation of key equipment is advancing well, with delivery to site of key components such as the Carbon-in-Leach ("CIL") tanks and grinding mills. Structural fills at the plant terrace were completed. Key areas, including crushing, grinding, and leaching, were handed over to the civil works contractor, allowing rebar installation and concrete works. Key bulk earthworks progress outside the process plant area was achieved ahead of the rainy season. Structural, Mechanical, Plate and Piping $(SMPP)$ contractor fabrication is progressing well, and development of the main accommodation camp is nearing completion. Mobilization of the mining fleet is ongoing with the site delivery expected imminently, and mining pioneering was completed during the quarter.

For the quarter ended June 30, 2025, $71.3 million was spent on the Kurmuk project, comprising direct construction capital expenditures and exploration activity.

The Company remains positioned to achieve the next milestones, which include:

   -- Bulk mining activities start in third quarter 2025 
 
          -- Completion of engineering in third quarter 2025 
 
          -- Mechanical erection ramp-up in third quarter 2025 in CIL area 
 
          -- CIL area completed in first quarter 2026 
 
          -- Power line completion in first quarter 2026 
 
          -- Commissioning start in second quarter 2026 
 
          -- First gold in second quarter 2026 

A November update is planned for Kurmuk Mineral Resources and Mineral Reserves, in relation to the infill drilling effort carried thus far to support the start of mining activities, along with an exploration update on the different targets throughout the property. The Company expects Kurmuk to produce an average of 290,000 ounces per year for the first four years and 240,000 ounces per year on average for the mine's life, with AISC(1) below $950 per ounce.

Sadiola Phased Expansion: The first phase of expansion at Sadiola advanced on schedule and on budget during the second quarter. Earthworks, civil works and structural fill, along with engineering and procurement, are progressing well with engineering and procurement essentially complete. The first components of the modular three-stage crushing plant have been shipped to site, and preparatory earthworks in the area have commenced. The mill motor has landed on site, as have the mill components. The first batch of structural steel has arrived on site and erection will commence imminently. Major mechanical equipment, including the cyclones and pumps are en route and will arrive on site for installation during the third quarter. The current third quarter focus will be on installation of structural steel and mechanical equipment allowing for follow-on completion of the electrical, control and instrumentation installation scope and commissioning in the fourth quarter.

Continued investment in the first phase expansion, including planned plant modifications and infrastructure upgrades, is consistent with prior estimates at $70 million in 2025. The first phase plant expansion involves installing additional crushing and grinding capacity in one of the processing plant lines, which will be dedicated to treating fresh ore. These modifications will allow Sadiola to treat up to 60% of fresh rock at a rate of up to 5.7 Mt/y in the modified process plant. With the completion of the first phase expansion, Sadiola is expected to produce between 200,000 and 230,000 ounces of gold per year in the medium term, ahead of the next expansion phase.

The Phase 2 Expansion, planned as a new processing plant to be built beginning in late 2026 and dedicated to processing fresh rock and oxides at a rate of up to 10 Mt per year, targeted to start production in late 2028, is expected to increase production to an average of 400,000 ounces per year for the first four years and 300,000 ounces per year on average for the mine's life, with AISC(1) expected to decrease to below $1,200 per gold ounce.

Strategic Initiatives Highlights

Allied executed a number of strategic transactions and initiatives during the second quarter, reinforcing a fortress balance sheet, further improving the Company's financial flexibility, enhancing trading liquidity and broadening the shareholder base. The transactions include:

   -- Sadiola Strategic Arrangements 

In the process of reviewing its power needs and overall power supply strategy, particularly in relation to Sadiola, the Company engaged with several parties over the course of the year, and it previously announced that it was negotiating a broader arrangement that included a power supply agreement and a sale of a portion of the Company's ownership in Sadiola with Ambrosia Investment Holding ("Ambrosia"). Subsequently, the Company also received a proposal from a third party for the purchase of a portion of Sadiola, on comparable terms. While the Company continues discussions relating to possible broader corporate transactions with Ambrosia and others, Allied has determined that selling any portion of Sadiola should not be undertaken at this time, and the pursuit of a power solution for Sadiola should be undertaken independently of broader corporate or asset level transactions. In addition to available independent power solutions being better priced and scaled, there has been considerable advancement with Sadiola that supports considerably greater value.

The Company has significantly advanced its analysis of power supply requirements for various expansion scenarios at Sadiola following the Phase 1 expansion. It has made substantial progress in assessing and negotiating the implementation of robust, proven, self-sufficient, pure-power solutions with experienced African power generation specialists. These solutions are tailored to the phased expansion approach at Sadiola, allowing for the progressive implementation of sustainable and reliable off-grid solutions. These pure-power solutions will enable the Company to deploy the optimal renewable energy penetration rate for each stage of the expansion project, improving energy supply reliability at all times, and achieving meaningful medium-term savings over the next five years, while remaining competitive in the longer term compared to the Ambrosia proposal, which had a higher capital intensity associated with a large-scale solar plant covering the requirements of the Phase 1 expansion, that led to meaningfully higher costs of power in the short to medium term.

Given the results of this process and the strategic relevance of self-reliant power supply, which has become a stated goal of the government in Mali, the Company has decided to advance the implementation of a self-reliant power generation solution for the site. This enables the Company to pursue an optimal solution for Sadiola, in collaboration with specialized and renowned partners, and where the Company also holds a significant ownership interest in the energy infrastructure. The Company is currently completing negotiations with a select group of companies for the long-term supply of energy to Sadiola. The solutions propose a phased deployment of a combination of off-grid thermal generation and solar-battery energy sources, offering a competitive levelized cost of energy compared to previous studies and the market. Allied expects to settle the framework agreements imminently and complete contract negotiations by the beginning of the fourth quarter of 2025. Amongst the many advantages of this solution, it creates more efficiency than pure solar alone, is cost effective and it is scalable to accommodate the larger expansion of Phase 2, or the incremental expansions between Phases 1 and 2 whose technical studies are being completed.

The Company concluded that it is able to execute its development strategy for Sadiola without the need to divest any stake in the asset, retaining ownership and gold-price leverage of a high-quality asset and exploration portfolio that has increased in value since the beginning of the year. Sadiola continues to stand out as a Tier-1 asset, underpinned by a strong operational base, significant mineral reserves and a leading production growth profile.

This confidence, and reasons to maintain full ownership of the asset and seek better terms with another power-solution partner, is supported by gold prices being substantially higher than at the time of engagement with the above-mentioned parties which significantly appreciates the value of the asset, the ongoing Phase 1 expansion being well advanced and on track for first gold production this year, improvements in governmental and other similar stakeholder engagements in Mali, a significantly improved and improving business environment in country, improved mine plans and management of the asset, and the advancement of engineering studies to assess the merits of a progressive expansion after Phase 1. This progressive approach targets reduced capital requirements in the medium term, leveraging the existing processing infrastructure. Furthermore, Allied is advancing test-work and engineering studies aimed to meaningfully increase metallurgical recoveries through the implementation of flotation and concentrate leaching as an add-on to the project. In addition to these technical studies and opportunities aimed at unlocking significant value and optionality, Allied has made significant progress on developing new oxide targets near mine, and is actively pursuing their conversion to mineral inventories and potential development, supported by an increased exploration budget and drilling program at Sadiola, focused on near-plant oxide opportunities.

As noted, Allied has positioned itself as a reliable partner with the Malian government, being the first company to adopt a new mining protocol in light of the 2023 mining code. The Company continues advancing discussions with SOREM (Mali state-owned mining company) to pursue potential mining opportunities in the vicinity of Sadiola and other highly prolific areas in Mali. While definitive arrangements have not been concluded at this time, the Company is in advanced discussions and is encouraged with the prospects under evaluation and the cooperativeness and ongoing engagement with in-country authorities.

With all of these regional, economical and technical factors considered, the Company believes that the implied value of Sadiola has increased significantly during a time coincident with the Company's conclusion that pursuing a self-reliant independent and optimized power solution is a better way to create value.

   -- New York Stock Exchange Listing: Allied began trading on the NYSE under 
      the ticker symbol AAUC on June 9, 2025. Allied believes that listing on 
      the NYSE will provide the Company with, among other things, access to a 
      broader investor audience, increased sources of potential capital, 
      improved trading liquidity in Allied's common shares, and increased 
      research coverage from U.S. investment banks. Finally, the listing is 
      expected to provide the opportunity for broader index inclusion. 
 
   -- Common Share Consolidation: In May of 2025, and in connection with the 
      Company's application to list its common shares on the NYSE, the Company 
      completed a share consolidation on the basis of one post-consolidation 
      common share for every three pre-consolidation common shares outstanding. 
 
   -- Bought Deal Public Offering and Concurrent Block Trade: During the 
      quarter, in April of 2025, the Company successfully closed on a bought 
      deal public offering, and a significant shareholder of the Company 
      completed a concurrent block trade transaction of common shares owned by 
      such shareholder. The offering was for an aggregate of 17,250,000 common 
      shares at a price of C$5.35 per share (on a pre-consolidation basis) for 
      aggregate gross proceeds of $66.8 million and net proceeds of $61.9 
      million. 

Enhancing market liquidity remains a key objective for the Company. Over the past 18 months, average daily trading volume, measured over a 20-day period, has increased approximately ninefold. The significant shareholder's block trade and the Company's offering further improved trading liquidity in advance of the Company's listing on the New York Stock Exchange. These transactions also support broader index inclusion and additional investor interest, all of which should help the Company's share price better reflect the Company's intrinsic value per share.

The Company intends to use the net proceeds from the offering to fund its optimization and growth initiatives, including advancing studies and engineering work to improve recoveries at Sadiola, supporting exploration and mine life extension studies in Côte d'Ivoire, and conducting additional exploration and development activities across its broader asset portfolio. The proceeds of the offering are expected to assist the Company in accelerating value creation from these assets and associated activities.

   -- Zero-Cost Collar Execution: On May 7, 2025, the Company completed a gold 
      price protection program that ensures a minimum price of $3,048 per ounce 
      and full upside to $4,000 per ounce on gold production of 15,500 ounces 
      per month from June 2025 through to March 2026, equalling a total of 
      155,000 ounces. Inclusive of already existing gold production under 
      preceding gold price protection through March of 2026, this represents 
      approximately 75% of total production in that period, thereby ensuring 
      higher margins and cash flows as the Company completes the development of 
      Kurmuk. 

Sustainability, Health and Safety Highlights

   -- The Company did not report any significant Environmental Incidents for 
      the three months ended on June 30, 2025. 
 
   -- The Company's Total Recordable Injury Rate (TRIR) was 0.87, compared to a 
      TRIR of 1.08 in the comparative prior year quarter. 
 
   -- In terms of Lost Time Injuries ("LTI"), the Company reported two LTI for 
      the three months ended June 30, 2025, compared to two LTI in the 
      comparative prior year quarter, which results in a Company Lost Time 
      Injury rate ("LTIR") for the three months ended June 30, 2025 of 0.35, 
      compared to a LTIR of 0.54 in the comparative prior year quarter. 

Summary of Operational Results

 
                                               For three months 
                                                 ended June 30, 
                                                           2025 
--------------------------------     -------------------------- 
Gold ounces 
 Production                                              91,017 
 Sales(8)                                                81,103 
Per Gold Ounce Sold 
 Total Cost of Sales(4)              $                    2,294 
 Cash Costs(1)                       $                    2,034 
 AISC(1)                             $                    2,343 
 
Average revenue per ounce            $                    3,098 
Average market price per ounce*      $                    3,280 
-----------------------------------  -------------------------- 
 
 
*Average market prices based on the LBMA PM Fix Price 
 

Gold production of 91,017 ounces during the three months ended June 30, 2025, was in line with expectations and driven by strong performance at Bonikro and Sadiola. As previously disclosed, production for the year is expected to follow a 45%/55% weighting between the first and second half, with the fourth quarter being the strongest of the year.

Total cost of sales(4) on a per gold ounce sold basis of $2,294 for the three months ended June 30, 2025. Cash costs(1) on a per gold ounce sold basis of $2,034 for the three months ended June 30, 2025. AISC(1) on a per ounce gold sold basis for the current quarter of $2,343. As described in the Company's annual guidance, every $100 per ounce increase in the price of gold results in $15 per ounce higher consolidated AISC(1) , which was based on a baseline for guidance of $2,500 per ounce, and at an average realized price in excess of $3,250 per ounce for the second quarter, consolidated AISC(1) was impacted by over $100 per ounce, impacting all mines, but disproportionately higher at Sadiola where gold price alone resulted in a $250 per ounce increase. At Bonikro, all unitary costs metrics were in line with plan. At Agbaou, following a plan for longer term optimization and increases in mine life, the Company prioritized waste removal over ore extraction to manage storm-water inflows into the pit and to secure access to higher-grade ore in the second half of 2025 as well as to support increased operational flexibility and production levels in 2026. Stripping costs in the second quarter, in the amount of $13.2 million, had a large impact on AISC(1) over the 14,938 ounces sold. Mine sequencing and the increase in stripping resulted in approximately $850 more AISC(1) per ounce in relation to the first quarter of 2025. While waste movement is expected to continue at similar levels for the remainder of the year, ore feed, gold grades and production are expected to materially increase quarter over quarter, resulting in reduced costs and increased cash flows in the second half of the year. Consequently, annual production for Agbaou, and the benefits in the second half of the year, results in a production expectation at the mid-point of guidance of approximately 83,500 ounces. In addition to operational factors, increased waste removal in 2025 allows for less reliance on short-term resource conversion to support production levels in 2026, creating a bridge to focus additional exploration spending at Agbaou on more transformational targets aimed at adding ounces and with an objective to increase mine life at Agbaou by four to six years, with the completion of the first stage exploration program in 2026. Production in 2026 is expected to further increase from the current year.

At Sadiola, as previously disclosed, the 2023 mining code is expected to impact costs by approximately $240 to $300 per ounce, with Korali-Sud attracting further government and third-party royalty burdens of an additional $200 per ounce, as it is subject to the full impact of the 2023 mining code without derogation of royalties. With continued contributions from Korali-Sud during the quarter, costs were impacted commensurately. Sadiola costs in the first quarter of 2025 were positively impacted by the sale of significant levels of Korali inventory from 2024. Had those ounces not been sold in the first quarter of 2025, Sadiola AISC(1) would have been approximately $2,150. As such, the change in costs in the second quarter over the first quarter is predominantly from the higher gold price and its impact on royalties. When compared to the prior year comparative quarter, increased gold prices and the 2023 mining code have resulted in an impact of approximately $600 per ounce in the Sadiola structure year-over-year.

Gold sales(8) of 81,103 ounces for the quarter ended June 30, 2025 compared to 84,611 ounces sold in the comparative quarter. Gold sales differed from production due to the timing of gold pours and final shipments before quarter end. The resulting build-up in finished goods inventory has been sold in July.

Average revenue per ounce generally diverges modestly from the average market price due to the impact of ounces delivered under the streams.

Sadiola (80% interest), Mali

Sadiola comprises the Sadiola (80% interest) open pit gold mine, located in the Kayes region of Mali, as well as the Korali-Sud open pit gold mine (65% interest), 15 kilometres south of the processing plant at Sadiola. The remaining ownership in Sadiola is retained by the Government of Mali.

 
                                                        For three months 
                                                          ended June 30, 
------------------------------------------- 
Sadiola Key Performance Information 
 (100% Basis)                                                       2025 
-------------------------------------------     ------------------------ 
Operating 
 Ore mined (M tonnes)                                               1.55 
 Waste mined (M tonnes)                                             6.10 
 Ore processed (M tonnes)                                           1.29 
Gold 
 Production (Ounces)                                              49,283 
 Sales(8) (Ounces)                                                43,648 
 Feed grade (g/t)                                                   1.31 
 Recovery rate (%)                                                89.1 % 
 Total cost of sales per ounce sold(4)           $                 2,493 
 Cash costs per ounce sold(1)                    $                 2,351 
 AISC per ounce sold(1)                          $                 2,471 
Financial (In thousands of US Dollars) 
 Revenue                                           $             138,985 
 Cost of sales (excluding DDA)                                 (103,175) 
----------------------------------------------  ------------------------ 
 Gross profit excluding DDA(1)                    $               35,810 
 DDA                                                             (5,635) 
----------------------------------------------  ------------------------ 
 Gross Profit                                     $               30,175 
----------------------------------------------  ------------------------ 
Capital Expenditures (In thousands of US 
Dollars) 
 Sustaining                                     $                    978 
 Expansionary                                                     20,194 
 Exploration                                                          40 
----------------------------------------------  ------------------------ 
 

For the three months ended June 30, 2025, Sadiola produced 49,283 ounces of gold. Production in the quarter was in line with plan and annual guidance, and includes the continued contribution from Korali-Sud high-grade oxide ore, as well as its fresh ore, through co-processing of Sadiola and Korali ores. Co-processing started on May 6, 2025 and is expected to continue into the third quarter of 2025. This initiative maximizes production, with clay content from Korali-Sud being mitigated by ore coming from Sadiola. Production is now fully supported by active pit mining, ending reliance on stockpiles, while unlocking improved grade control and mine-to-mill predictability, which sets a stronger base for long-term cost management. The Company is actively evaluating the future contribution of Korali-Sud and other new sources of oxide ore identified within the Sadiola mining licence with an update expected to be provided in due course. Oxide ore is favoured in the short term as it provides the plant with relatively inexpensive, high quality ounces.

Instrumentation upgrades to the process-plant are progressing with improvements in throughput, delivering an additional 171,000 tonnes from January through to May, resulting in over 5,900 more recovered ounces during the this period in relation to plan. Further savings in elution reagent costs are expected, driven by a reassessment of reagent-rate value calculations. Additional improvements include optimization of the regrind mill cyclone performance, and an upgrade to the feed-pump capacity at the processing plant. Once completed, further gains in throughput and recovery are expected. Commissioning of the Phase 1 process plant upgrade will supplement the ongoing instrumentation upgrade efforts.

At Sadiola, as previously disclosed, the 2023 mining code is expected to impact costs by approximately $240 to $300 per ounce, with Korali-Sud attracting further government and third-party royalty burdens of an additional $200 per ounce, as it is subject to the full impact of the 2023 mining code without derogation of royalties. With continued contributions from Korali-Sud during the quarter, costs were impacted commensurately. Sadiola costs in the first quarter of 2025 were positively impacted by the sale of significant levels of Korali inventory from 2024. Had those ounces not been sold in the first quarter of 2025, Sadiola AISC(1) would have been approximately $2,150. As such, the change in costs in the second quarter over the first quarter is predominantly from the higher gold price and its impact on royalties.

AISC(1) for the quarter was $2,471 per gold ounce. As described in the Company's annual guidance, every $100 per ounce increase in the price of gold results in $15 per ounce higher consolidated AISC(1) , which was based on a baseline for guidance of $2,500 per ounce, and at an average realized price in excess of $3,250 per ounce for the second quarter, consolidated AISC(1) was impacted by over $100 per ounce, impacting all mines, but disproportionately higher at Sadiola where gold price alone resulted in a $250 per ounce increase.

Sadiola Expansion Project and Korali-Sud

The first phase of expansion at Sadiola broke ground in the fourth quarter of 2024 and advanced on schedule and on budget during the second quarter. Earthworks, civil works and structural fill, along with engineering and procurement, are progressing well with engineering and procurement essentially complete. The first components of the modular three-stage crushing plant have been shipped to site, and preparatory earthworks in the area have commenced. The mill motor has landed on site, as have the mill components. The first batch of structural steel has arrived on site and erection will commence imminently. Major mechanical equipment, including the cyclones and pumps are en route and will arrive on site for installation during the third quarter. The current third quarter focus will be on installation of structural steel and mechanical equipment allowing for follow-on completion of the electrical, control and instrumentation installation, and commissioning in the fourth quarter.

Continued investment in the first phase expansion, including planned plant modifications and infrastructure upgrades, is consistent with prior estimates at $70 million in 2025. The first phase plant expansion involves installing additional crushing and grinding capacity in one of the processing plant lines, which will be dedicated to treating fresh ore. These modifications will allow Sadiola to treat up to 60% of fresh rock at a rate of up to 5.7 Mt/y in the modified process plant starting during the fourth quarter of 2025. With the completion of plant modifications in the first phase, Sadiola is expected to stabilize and produce between 200,000 and 230,000 ounces of gold per year in the medium term, ahead of the next phase of expansion. The Phase 2 Expansion, planned as a new processing plant with planned project commencement in late 2026 and dedicated to processing fresh rock and oxides at a rate of up to 10 Mt per year, targeted to start production in late 2028, is expected to increase production to an average of 400,000 ounces per year for the first four years and 300,000 ounces per year on average for the mine's life, with AISC(1) expected to decrease to below $1,200 per gold ounce.

Further, the Company is conducting engineering studies to determine the optimal path for a progressive, phased expansion of the existing plant beyond the year 2025, with the objective to target similar ultimate production levels at improved capital intensity. This will be achieved by advancing opportunities for optimization of the Sadiola Gold Mine Expansion Projects, including metallurgical test work and a pre-feasibility study to potentially increase recoveries by over 10 percentage points through the use of flotation and concentrate leaching. The progressive expansion would facilitate treatment of Fresh Ores, potentially reducing the requirements for a future single, major capital expenditure and accelerating gold production through increased plant throughput. These studies, supported by the Company's phased investment, seek to improve Sadiola's financial performance significantly. With this long-term and value-focused strategy, the Company is well-positioned to affirm that the advancement of the Sadiola Gold Mine Project is proceeding as planned, reinforcing Allied's commitment to operational excellence and long-term value creation.

Sadiola Exploration

Since acquiring the Sadiola Project in 2021, Allied has identified over 15 million tonnes of economic oxide mineralization within the near-mine footprint, significantly enhancing the oxide resource base critical for the existing and planned processing infrastructure. Ongoing exploration activities at Sekekoto West, FE4, FE2 Trend and Tambali South are crucial to Allied's strategy to leverage the existing resources and infrastructure to maximize production and cash flows in the short term.

During the quarter, exploratory and resource drilling programs were conducted on the Sadiola licence. A total of 273 holes were drilled totalling 24,627 metres by five exploration drill rigs. Resource and exploratory drilling programs continued and were expanded at the Sekekoto West, Tambali and FE4 deposits, and at the FE2.5 prospect during the quarter. A sterilization drill program over a proposed new tailings storage facility, to the east of Sadiola Mine continued and is expected to be completed in the third quarter.

Exploratory drilling at Sekekoto West deposit was extended to the north during the quarter with drillhole intersections demonstrating that the deposit remains open 500 metres to the north outside of the current pit designs. Further drilling is planned to continue testing for strike extensions of this mineralized trend to the north and south.

At the Tambali deposit, deeper core drilling of the fresh rock mineralization is being carried out on 100 metre section lines with a goal to be completed in the third quarter of 2025. Drillhole intersections demonstrate good continuity of economic mineralization to 320 metres depth. An updated geological model completed in the second quarter will provide guidance for further drill testing of this deposit in subsequent programs.

At FE4, a 199-hole drill program, now 29% completed, is being carried out to both upgrade inferred mineral resources to Indicated and test for extensions to the known mineralization. Results to date have been encouraging.

Drilling continued to the north of the 1.1 kilometre-long FE2.5 oxide gold prospect and extended oxide gold mineralization for another 1.1 kilometres further north to the south end of the historic 1.2 kilometre long FE2 pit. Oxide gold mineralization has now been followed, more or less continuously for 3.4 kilometres and is open to the north and, less so, to the south. Drilling will continue to test this limestone/clastic sediment trend with wide-spaced holes for another 2 kilometres to the north of the FE2 pit with a goal to exhibit potential for shallow oxide gold resources along the entire 5.5 kilometre long trend. Once the scope of the mineralization is defined, a systematic program of resource conversion will be carried out as required.

Further, Sadiola will also see continued efforts with five drills dedicated to continue testing for and extending the gold mineralized structures at Sadiola Main, Tambali, FE2 Trend, Sekekoto Trend and FE4 with a further budget of $5.7 million. The exploration is focused on both oxide and fresh mineralization with a preference for oxide gold mineralization in the near term. Oxide ore is favoured in the short term as it provides the plant with relatively inexpensive, high quality ounces. The horizontal and down-dip/down-plunge limits of these systems have not been defined yet and expectations of ongoing discovery/additions are high. A sixth drill will begin to follow up on other mineralized structures/ideas over the property area.

Bonikro (89.89% interest), Côte d'Ivoire

The Bonikro gold mine is an open pit gold mine located in the Oumé region of Côte d'Ivoire ("Bonikro" or "Bonikro Mine"). The remaining ownership is split between the Government of Côte d'Ivoire (10%) and a local minority shareholder (0.11%).

Bonikro is contiguous to Agbaou, and together they comprise the CDI Complex, with the two processing plants located only 20 km from each other. The combined milling capacity and existing infrastructure including water supply dams, tailings storage facilities, access and site roads, power supply and accommodation facilities, provide optionality and significant synergies.

Bonikro comprises two separate mining licences (the Bonikro Licence and Hiré Licence), although integrated as a single operation.

 
                                                        For three months 
                                                          ended June 30, 
-------------------------------------------- 
Bonikro Key Performance Information 
 (100% Basis)                                                       2025 
--------------------------------------------     ----------------------- 
Operating 
 Ore mined (M tonnes)                                               0.59 
 Waste mined (M tonnes)                                             5.05 
 Ore processed (M tonnes)                                           0.63 
Gold 
 Production (Ounces)                                              25,775 
 Sales (Ounces)                                                   22,517 
 Feed grade (g/t)                                                   1.26 
 Recovery rate (%)                                                95.0 % 
 Total cost of sales per ounce sold(4)           $                 1,928 
 Cash costs per ounce sold(1)                    $                 1,384 
 AISC per ounce sold(1)                          $                 1,592 
Financial (In thousands of US Dollars) 
 Revenue                                          $               66,564 
 Cost of sales (excluding DDA)                                  (31,361) 
-----------------------------------------------  ----------------------- 
 Gross profit excluding DDA(1)                    $               35,203 
 DDA                                                            (12,056) 
-----------------------------------------------  ----------------------- 
 Gross Profit                                     $               23,147 
-----------------------------------------------  ----------------------- 
Capital Expenditures (In thousands of US 
Dollars) 
 Sustaining                                       $               12,877 
 Expansionary                                                         -- 
 Exploration                                                       2,292 
-----------------------------------------------  ----------------------- 
 

Bonikro produced 25,775 ounces of gold during the three months ended June 30, 2025, in line with plan and annual guidance. The strong production was driven by higher grade ore mined from PB3, and improved throughput and recovered grade in the process plant. Improved plant throughput was achieved with the completion of plant enhancements, increased crusher availability, improved fragmentation, and enhanced maintenance practices.

Bonikro remained on plan in the quarter, benefiting from mine sequencing into higher-grade zones and stable plant performance. Throughput improved following enhancements to the comminution circuit, including screen panel modifications that lifted mill rates by nearly 9%. Gains were also supported by better crusher availability and proactive maintenance routines.

The ongoing stripping campaign at PB3 and PB5 in the first half of the year positions the Company on track to expose higher-grade material for the last quarter of 2025, as well as the following years, with minimal waste stripping expected during 2026 and 2027. This mining sequencing at Bonikro, for an anticipated $60 million of capital expenditures related to production stripping during 2025, will lead to robust free cash flows, as the stripping ratio decreases and it further exposes higher-grade ore. As the waste stripping benefits not only 2025 but also the following two years of production, the AISC(1) per ounce sold figure accounts for the allocation of the stripping spend over the ounces it benefits through 2027.

The Company has now succeeded in implementing a centralized management model for both mines in CDI, streamlining processes, optimizing resources, and enhancing service delivery for sustainable growth, and lowering AISC(1) . The Company anticipates waste stripping in the third quarter at similar levels than that completed during the second quarter, after which Bonikro PB5 be able to provide higher-grade ore for the remaining years of its current life. Costs for the period were in line with plan.

Gold sales differed from production due to the timing of gold pours and final shipments before quarter end. The resulting build-up in finished goods inventory has been sold in July.

Hiré and Oumé Exploration

Resource and exploration drilling was conducted during the quarter on the Company's mining licences and exploration licences.

At the Hiré mine, three rigs defined relatively narrow lenses of oxide gold mineralization traceable for 550 metres and 1,100 metres at the Assondji-So Marais and Assondji-So South areas, respectively. Both of these zones lie within the southwest part of the compensation area with mineralization expected to extend to the west outside of the permitted area. Work to further extend the Assondji So South mineralization, to the southwest, is expected to begin in the third quarter. Scout drilling also started immediately south of the Assondji So pit over an area of historic artisanal workings. This work is expected to continue into the third quarter. A program is also planned to commence in the third quarter to test the underground potential of the gold mineralization below the Akissi So pit.

Oumé Exploration

At the Oumé Project, drilling to convert Inferred mineral resources to Indicated mineral resources was completed at the Dougbafla North prospect with some holes designed to extend the zone across strike and to depth. Drilling resumed over the Dougbafla West deposit with a goal to infill and extend the mineralized lenses with drilling continuing into the third quarter. Exploration work plans have been proposed to the east of the Dougbafla Central zone and SW of the Dougbafla West Prospect as the limits of the Oumé mineralized systems have not been defined yet. One of the goals of the step out drilling is to identify additional felsic intrusions along the shear corridor where wider mineralized zones would be expected.

Agbaou (85% interest), Côte d'Ivoire

Agbaou is an open pit gold mine, located in the Oumé region of Côte d'Ivoire. The remaining ownership is split between the Government of Côte d'Ivoire (10%) and the SODEMI development agency (5%).

Agbaou is contiguous to Bonikro, and together they comprise the CDI Complex, with the two processing plants located only 20 km from each other.

 
                                                        For three months 
                                                          ended June 30, 
-------------------------------------------- 
Agbaou Key Performance Information 
 (100% Basis)                                                       2025 
--------------------------------------------     ----------------------- 
Operating 
 Ore mined (M tonnes)                                               0.41 
 Waste mined (M tonnes)                                             9.71 
 Ore processed (M tonnes)                                           0.59 
Gold 
 Production (Ounces)                                              15,959 
 Sales (Ounces)                                                   14,938 
 Feed grade (g/t)                                                   0.89 
 Recovery rate (%)                                                94.7 % 
 Total cost of sales per ounce sold(4)           $                 2,267 
 Cash costs per ounce sold(1)                    $                 2,085 
 AISC per ounce sold(1)                          $                 3,104 
Financial (In thousands of US Dollars) 
 Revenue                                          $               46,430 
 Cost of sales (excluding DDA)                                  (30,366) 
-----------------------------------------------  ----------------------- 
 Gross profit excluding DDA(1)                    $               16,064 
 DDA                                                             (3,495) 
-----------------------------------------------  ----------------------- 
 Gross Profit                                     $               12,569 
-----------------------------------------------  ----------------------- 
Capital Expenditures (In thousands of US 
Dollars) 
 Sustaining                                       $               13,721 
 Expansionary                                                         -- 
 Exploration                                                         989 
-----------------------------------------------  ----------------------- 
 

Agbaou produced 15,959 ounces of gold during the three months ended June 30, 2025, and aligned with the revised mine sequence. Production in the quarter was the result of higher oxide grade mined in the Agbale pit and treated at Agbaou. This allowed for increased throughput in the process plant. The performance was supported by mining fleet performance optimization and the implementation of enhanced short-interval controls.

At Agbaou, the Company prioritized waste removal over ore extraction to manage storm-water inflows into the pit and to secure access to higher-grade ore in the second half of 2025 as well as to support increased operational flexibility and production levels in 2026. Stripping spend in the second quarter, which amounted to $17.9 million, had a large impact on AISC(1) over the 14,938 ounces sold. While waste movement is expected to continue at similar levels for the remainder of the year, ore feed, gold grades and production are expected to materially increase quarter over quarter, resulting in reduced costs and increased cash flows in the second half of the year. In addition to operational factors, increased waste removal in 2025 allows for less reliance on short-term resource conversion to support production levels in 2026, creating a bridge to focus additional exploration spending at Agbaou on more transformational targets aimed to add ounces and with an objective to increase mine life at Agbaou by four to six years, with the completion of the first stage exploration program in 2026. Production in 2026 is expected to further increase from the current year.

The Company has now succeeded in implementing a centralized management model for both mines in CDI, streamlining processes, optimizing resources, and enhancing service delivery for sustainable growth, and lowering AISC(1) . The benefits of the centralized contractor model and the Hub-and-Spoke structure implemented are becoming more evident, enabling improved agility in managing shared resources and coordinating recovery efforts across sites. These enablers will be further embedded in the coming months as the Company transitions from initiation to full execution. Looking ahead, execution discipline will remain central to delivering value in the second half. With deeper integration of the Hub-and-Spoke model, continued focus on plant optimization, and improved mining flexibility.

Costs for the second quarter, as anticipated, reflect the significant increase in stripping at WP 7, which will benefit access to oxide ore in the later part of 2025, partially offset by the successful implementation of a centralized management model. This is expected to result in higher production at lower costs for the remainder of 2025, as second half of the year sustaining capital significant decreases in the third quarter, and is minimal in the fourth quarter.

Gold sales differed from production due to the timing of gold pours and final shipments before quarter end. The resulting build-up in finished goods inventory has been sold in July.

Agbaou Exploration

Allied is actively pursuing opportunities to extend the mine life by increasing Mineral Reserves through sustained drilling and other exploration efforts. In the second quarter of 2025, with a further budget of $7.5 million for the year, the Company launched a focused initiative comprising two strategic projects aimed at accelerating this objective.

The first project targets the Agbaou West and East pits, with the goal of upgrading Inferred Mineral Resources to Indicated Mineral Resources to test for down dip extensions of known mineralization and to test for new lenses. The drilling campaign, structured in three phases, commenced in July, 2025, and is scheduled for completion in the first half of 2026. The program's goal is to add several more years to mine life.

The second project focuses on the Hire-Akissi So target, where the Company is working to confirm the presence of an underground mineable resource at grades ranging from 3 to 4 g/t of gold. This two-phase drilling program also commenced in July 2025, and is expected to conclude by late first quarter of 2026.

Allied anticipates reporting progress on these initiatives by delivering a program status update in the second quarter of 2026. Up to seven core drills will be devoted to these two programs with one other RC drill dedicated to testing new targets.

Kurmuk, (100% interest(7) ), Ethiopia

The Company continues to track well against plan for the Kurmuk Project, both in terms of physical completion and spend, having achieved key milestones and progress during the second quarter of 2025. The Company remains positioned to achieve the next milestones, which include:

   -- Bulk mining activities start in third quarter 2025, 
 
   -- Completion of engineering in third quarter 2025, 
 
   -- Mechanical erection ramp-up in third quarter 2025 in CIL area, 
 
   -- CIL area completed in first quarter 2026, 
 
   -- Power line completion in first quarter 2026, 
 
   -- Commissioning start in second quarter 2026, 
 
   -- First gold in second quarter 2026. 

Being less than a year away from first production, the Company is advancing technical studies aimed at improving operational confidence and flexibility, including potential increases in plant throughput among other improvements and targeted optimizations. The Company is also advancing a detailed review of the remaining aspects of the project, including project supply chain and logistics. Notable quarterly updates include:

   -- Engineering and Procurement have achieved approximately 90% progress. 
      Transportation of key equipment is advancing well, with delivery to site 
      of key components such as the Carbon-in-Leach ("CIL") tanks and grinding 
      mills. 
 
          -- Structural fills at the plant terrace were completed. 
 
          -- Critical areas including crushing, grinding, and CIL were handed 
             over to the civil contractor, allowing rebar installation and 
             concrete works: 
 
                 -- Foundation work for all CIL tanks and thickeners is 
                    complete and handed over to the Structural, Mechanical, 
                    Plate and Piping ("SMPP") contractor. 
 
                 -- Concrete casting for both the SAG and Ball mill has been 
                    finalized, marking a key milestone in plant infrastructure 
                    readiness. 
 
                 -- Works are progressing on the primary crusher, stockpile 
                    tunnel, process water tanks, and reagents facilities in 
                    line with the schedule. 
 
          -- Key bulk earthworks progress outside the process plant area was 
             achieved ahead of the rainy season, including: 
 
                 -- Substantial completion of the water storage dam, a critical 
                    milestone for water capture ahead of the wet season. 
 
                 -- The construction of the explosives magazine facilities is 
                    progressing as planned, with work on track to support the 
                    scheduled arrival of the first explosives on site. 
 
                 -- The construction of the airstrip has been completed, 
                    marking a key logistics, safety and security milestone for 
                    the project. 
 
          -- SMPP contractor fabrication is progressing well, and site 
             mobilization is advancing through a phased approach focused on 
             erecting the permanent camp ancillary facilities. 
 
          -- Development of the main accommodation camp is nearing completion, 
             with key support facilities including a 1,200-person kitchen, 
             administration building, clinic, and laundry being actively 
             managed to accommodate the project's expanding workforce and 
             mobilization needs. 
 
          -- Mobilization of the mining fleet is ongoing with the site delivery 
             expected imminently. 
 
          -- Meanwhile, the Company completed pioneering mining activities for 
             the establishment of access and infrastructure. Mining activities 
             will continue throughout the year and into 2026, with the 
             objective of preparing the mine and building ore stockpiles to 
             support the commissioning stage and the start of operations. 

Kurmuk is expected to produce first gold by mid-2026, contributing an estimated 175,000 ounces of gold in the second half of 2026. On a year-to-date basis, $127.4 million has been spent on the Kurmuk Project, comprising direct construction capital expenditures and exploration activity, with $71.3 million spent in the quarter.

A November update is planned for Kurmuk Mineral Resources and Mineral Reserves, in relation to the infill drilling effort carried thus far to support the start of mining activities, along with an exploration update on the different targets throughout the property.

Operational Summary

 
For 
three 
months 
ended     Production   Sales 
June 30,        Gold    Gold       Cost of Sales Per   Cash Cost(1) Per Gold             AISC(1) Per 
2025          Ounces  Ounces         Gold Ounce Sold              Ounce Sold         Gold Ounce Sold 
--------  ----------  ------  ----------------------  ----------------------  ---------------------- 
Sadiola 
 Gold 
 Mine         49,283  43,648  $                2,493  $                2,351  $                2,471 
Bonikro 
 Gold 
 Mine         25,775  22,517  $                1,928  $                1,384  $                1,592 
Agbaou 
 Gold 
 Mine         15,959  14,938  $                2,267  $                2,085  $                3,104 
--------  ----------  ------  ----------------------  ----------------------  ---------------------- 
Total         91,017  81,103  $                2,294  $                2,034  $                2,343 
--------  ----------  ------  ----------------------  ----------------------  ---------------------- 
 

FINANCIAL SUMMARY AND KEY STATISTICS

Key financial operating statistics for the second quarter 2025 are outlined in the following tables.

 
                                                 For three months ended June 30,                             For six months ended June 30, 
---------------------- 
(In thousands of US 
Dollars, except for 
shares and per share 
amounts) (Unaudited)                           2025                         2024                         2025                         2024 
----------------------  ---------------------------  ---------------------------  ---------------------------  --------------------------- 
Revenue                    $                251,979     $                195,614     $                598,386     $                370,681 
Cost of sales, 
 excluding 
 depreciation, 
 depletion and 
 amortization ("DDA")                     (164,902)                    (115,485)                    (372,694)                    (237,001) 
----------------------  ---------------------------  ---------------------------  ---------------------------  --------------------------- 
Gross profit excluding 
 DDA(1)                   $                  87,077    $                  80,129     $                225,692     $                133,680 
DDA                                        (21,186)                     (12,358)                     (40,143)                     (23,460) 
----------------------  ---------------------------  ---------------------------  ---------------------------  --------------------------- 
Gross profit              $                  65,891    $                  67,771     $                185,549     $                110,220 
General and 
 administrative 
 expenses                 $                (27,713)    $                (15,240)    $                (46,565)    $                (29,401) 
Exploration and 
 evaluation expenses                        (3,810)                      (3,054)                      (7,337)                      (7,884) 
Loss on revaluation of 
 financial instruments 
 and embedded 
 derivatives                               (13,971)                      (2,099)                     (28,087)                      (3,882) 
Other losses                               (18,621)                      (4,214)                     (17,493)                      (7,629) 
----------------------  ---------------------------  ---------------------------  ---------------------------  --------------------------- 
Net earnings before 
 finance costs and 
 income tax              $                    1,776    $                  43,164    $                  86,067    $                  61,424 
Finance costs                               (2,764)                      (7,082)                      (8,074)                     (12,719) 
----------------------  ---------------------------  ---------------------------  ---------------------------  --------------------------- 
Net (loss) earnings 
 before income tax                            (988)                       36,082                       77,993                       48,705 
----------------------  ---------------------------  ---------------------------  ---------------------------  --------------------------- 
Current income tax 
 expense                  $                (14,560)    $                (18,894)    $                (42,260)    $                (27,380) 
Deferred income tax 
 recovery (expense)                              24                        (769)                     (11,320)                      (5,748) 
----------------------  ---------------------------  ---------------------------  ---------------------------  --------------------------- 
Net (loss) earnings       $                (15,524)    $                  16,419    $                  24,413    $                  15,577 
----------------------  ---------------------------  ---------------------------  ---------------------------  --------------------------- 
 
(Loss) 
earnings attributable 
to: 
 Shareholders of the 
  Company                 $                (25,410)   $                    8,298    $                (10,286)   $                    2,613 
 Non-controlling 
  interests                                   9,886                        8,121                       34,699                       12,964 
----------------------  ---------------------------  ---------------------------  ---------------------------  --------------------------- 
Net (loss) earnings 
 for the period           $                (15,524)    $                  16,419    $                  24,413    $                  15,577 
----------------------  ---------------------------  ---------------------------  ---------------------------  --------------------------- 
 
Net (loss) earnings 
per share attributable 
to shareholders of the 
Company 
Basic                   $                    (0.22)  $                      0.10  $                    (0.09)  $                      0.03 
Diluted                 $                    (0.22)  $                      0.09  $                    (0.09)  $                      0.03 
----------------------  ---------------------------  ---------------------------  ---------------------------  --------------------------- 
 
 
                                            For three months ended June 30,                             For six months ended June 30, 
---------------- 
(In thousands of 
US Dollars, 
except per share 
amounts)                                 2025                          2024                         2025                         2024 
----------------  ---------------------------  ----------------------------  ---------------------------  --------------------------- 
Net (Loss) 
 Earnings 
 attributable to 
 Shareholders of 
 the Company        $                (25,410)    $                    8,298    $                (10,286)   $                    2,613 
----------------  ---------------------------  ----------------------------  ---------------------------  --------------------------- 
Net (Loss) 
Earnings 
attributable to 
Shareholders of                                $                      split 
the Company per                                             presentation to 
Share             $                    (0.22)                 basic/diluted  $                    (0.09)  $                      0.03 
 Loss on 
  revaluation of 
  financial 
  instrument                           13,971                         2,099                       28,087                        3,882 
 Depreciation of 
  Korali 
  share-based 
  payment for 
  permit                                  876                            --                        4,756                           -- 
 Foreign 
  exchange                                292                           568                        3,335                          832 
 Share-based 
  expense                              17,170                         2,011                       21,277                        4,138 
 Other 
  Adjustments(*)                       16,490                       (3,148)                       27,439                      (1,066) 
 Tax adjustments                      (7,168)                         1,805                     (13,314)                        2,159 
----------------  ---------------------------  ----------------------------  ---------------------------  --------------------------- 
Total increase 
 to Attributable 
 Net 
 Earnings(2)        $                  41,631    $                    3,335    $                  71,580   $                    9,945 
----------------  ---------------------------  ----------------------------  ---------------------------  --------------------------- 
Total increase 
 to Attributable 
 Net Earnings(2) 

(MORE TO FOLLOW) Dow Jones Newswires

August 06, 2025 18:22 ET (22:22 GMT)

At the request of the copyright holder, you need to log in to view this content

Disclaimer: Investing carries risk. This is not financial advice. The above content should not be regarded as an offer, recommendation, or solicitation on acquiring or disposing of any financial products, any associated discussions, comments, or posts by author or other users should not be considered as such either. It is solely for general information purpose only, which does not consider your own investment objectives, financial situations or needs. TTM assumes no responsibility or warranty for the accuracy and completeness of the information, investors should do their own research and may seek professional advice before investing.

Most Discussed

  1. 1
     
     
     
     
  2. 2
     
     
     
     
  3. 3
     
     
     
     
  4. 4
     
     
     
     
  5. 5
     
     
     
     
  6. 6
     
     
     
     
  7. 7
     
     
     
     
  8. 8
     
     
     
     
  9. 9
     
     
     
     
  10. 10