Sanli Environmental's Subsidiary Receives Letter from Customer Following Project Delays; Shares Down 9%
MT Newswires
Jan 05
Sanli Environmental's (SGX:1E3) subsidiary, Sanli M&E Engineering, received a letter from a customer, in connection with damages due to delays in the completion of certain phases of a project, according to a Monday filing with the Singapore Exchange.
The subsidiary had previously submitted applications for extension of time for the project, to which it is yet to receive a response.
To date, the parties have not agreed on any liquidated damages, with the company currently not in a position to determine the financial implications of the delays.
Shares of the water and waste management company plunged nearly 9% in Monday trading.
Disclaimer: Investing carries risk. This is not financial advice. The above content should not be regarded as an offer, recommendation, or solicitation on acquiring or disposing of any financial products, any associated discussions, comments, or posts by author or other users should not be considered as such either. It is solely for general information purpose only, which does not consider your own investment objectives, financial situations or needs. TTM assumes no responsibility or warranty for the accuracy and completeness of the information, investors should do their own research and may seek professional advice before investing.