Deep Yellow Says Detailed Engineering for Namibia Uranium Project Over 60% Complete
MT Newswires Live
Jan 22
Deep Yellow (ASX:DYL) said detailed engineering for the Tumas uranium project in Namibia is over 60% complete, and more than 70% of all major equipment for the process plant has now been tendered, according to a Thursday Australian bourse filing.
Orders for vendor data have been placed for all long lead equipment items, per the filing. Meanwhile, the bulk earthworks for the project started in October 2025, and are 24% complete. Talks with Namibia Water regarding the draft water supply agreement and draft development agreement are ongoing.
The company added that incoming Chief Executive Greg Field will start on Feb. 2.
Disclaimer: Investing carries risk. This is not financial advice. The above content should not be regarded as an offer, recommendation, or solicitation on acquiring or disposing of any financial products, any associated discussions, comments, or posts by author or other users should not be considered as such either. It is solely for general information purpose only, which does not consider your own investment objectives, financial situations or needs. TTM assumes no responsibility or warranty for the accuracy and completeness of the information, investors should do their own research and may seek professional advice before investing.