风芒能源获悉,2月2日,云南省玉溪市峨山县发展和改革局公示峨山县“双龙风电场”优选投资开发主体竞争性优选中选结果。公示显示,该项目由华润新能源(易门)有限公司中选。该项目竞配公告显示,峨山县“双龙风电场”项目装机规模3.75万千瓦。工期要求:取得项目开发权后1个月内启动前期工作;6个月内完成项目核准,取得核准后3个月内开工,原则上开工后1年具备投产条件,18个月实现全容量并网。因自身原因逾期未完成...
Source Link风芒能源获悉,2月2日,云南省玉溪市峨山县发展和改革局公示峨山县“双龙风电场”优选投资开发主体竞争性优选中选结果。公示显示,该项目由华润新能源(易门)有限公司中选。该项目竞配公告显示,峨山县“双龙风电场”项目装机规模3.75万千瓦。工期要求:取得项目开发权后1个月内启动前期工作;6个月内完成项目核准,取得核准后3个月内开工,原则上开工后1年具备投产条件,18个月实现全容量并网。因自身原因逾期未完成...
Source LinkDisclaimer: Investing carries risk. This is not financial advice. The above content should not be regarded as an offer, recommendation, or solicitation on acquiring or disposing of any financial products, any associated discussions, comments, or posts by author or other users should not be considered as such either. It is solely for general information purpose only, which does not consider your own investment objectives, financial situations or needs. TTM assumes no responsibility or warranty for the accuracy and completeness of the information, investors should do their own research and may seek professional advice before investing.