TSX:ORV
TORONTO, Feb. 11, 2026 /CNW/ - Orvana Minerals Corp. (TSX: ORV) (the "Company" or "Orvana") reports results for the quarter ended December 31, 2025 ("Q1 FY2026"), updates on the Oxides Stockpile Project at its Don Mario operation in Bolivia, and provides guidance for its Bolivian subsidiary, Empresa Minera Paitití, S.A. ("EMIPA") for Fiscal Year 2026 ("FY2026").
Juan Gavidia, CEO of Orvana, commented, "Our Bolivian operation has commenced trial processing of legacy ore through the Au-Ag circuit as part of the Don Mario plant restart. This represents an important operational step to resume metal production in Bolivia. The update and FY2026 guidance we are providing today reflect the significant efforts of the Bolivian team in advancing construction activities and preparing the operation for the phased ramp-up of production. I would like to congratulate the team for their dedication and execution under challenging conditions."
Highlights
Bolivia:
-- EMIPA has commenced operational trials by processing legacy sulfide ore
through the Au-Ag circuit as part of the Don Mario plant restart. Initial
doré production is expected to commence in the second half of
February 2026, subject to successful completion of performance
verification activities.
-- The next operational milestones include the completion of construction of
the Cu circuits and the phased integration of all processing circuits,
with commissioning expected to be fully completed early in the third
quarter of fiscal 2026.
-- Processing of the oxide stockpiles is expected to begin thereafter and to
ramp up progressively through the third quarter of fiscal 2026, with the
objective of achieving full operational capacity during the fourth
quarter of fiscal 2026. The timing and pace of ramp-up will depend on
plant performance, equipment reliability, and the optimization of
operating parameters.
-- As previously disclosed, EMIPA completed an on-site pilot test on
representative oxide material. Based on the results of this pilot test,
together with pre-existing metallurgical data, the Company has set forth
its planning for the processing of its oxide stockpiles. For fiscal 2026,
the plan assumes Au--Ag--Cu recoveries at levels below long-term
expectations, reflecting the early stages of ramp-up and the ongoing
optimization of process efficiency. Production and recovery rates are
expected to improve over time as operational practices are fine-tuned,
and equipment performance stabilizes.
-- Oxide Stockpiles- Production planning - The following table presents the
production planning for the oxide stockpile ore only (not including
legacy sulfide ore):
Oxide StockpilesProduction Planning H2 FY2026 FY2027 -- FY2029 Total
(1)
Oxides milled (dmt) 256,288 1,532,831 1,789,119
Gold
Grade (g/t) 1.85 1.85 1.85
Recovery (%) 85.5 94.0 92.8
Production (oz) 13,039 85,701 98,740
Silver
Grade (g/t) 42.72 42.72 42.72
Recovery (%) 74.7 76.5 76.2
Production (oz) 262,966 1,609,471 1,872,437
Copper
Grade (%) 1.87 1.87 1.87
Recovery (%) 71.2 78.0 77.0
Production ('000 lbs) 7,521 49,289 56,810
(1) The production estimates presented herein relate to
the oxide stockpile material only and are preliminary
in nature and are intended to provide an indicative
production planning only. They do not constitute mineral
reserves, a mine plan, or FY2026 production guidance.
Actual production results may vary materially, as
they depend on commissioning progress, plant performance,
equipment reliability and other operational factors.
These estimates should not be relied upon as definitive
projections. The production planning will be reviewed
and may be updated from time to time as additional
operating data becomes available. The estimation has
been reviewed and approved by Luis Isla, Chief of
Geology of EMIPA, a qualified person under NI 43-101
and an employee of the Company.
This production planning is distinct from, and should
not be confused with, the Company's FY2026 guidance
for EMIPA, which incorporates expected production
from both oxide stockpiles and legacy sulfide ore
processed during FY2026.
-- EMIPA -- FY2026 Guidance - The following table sets out EMIPA's FY2026
guidance for metal production and unitary costs(2), which reflects the
expected processing of both oxide stockpiles and legacy sulfide ore at
the Don Mario operation. The figures in the table below are based on
current assumptions regarding the completion of the plant expansion, and
subject to the commissioning and ramp-up performance of the Don Mario
plant. The total metal production expected for FY2026 is based on the
planned processing of 256,288 tonnes of oxide ore and approximately
65,000 tonnes of legacy sulfide ore.
FY2026Guidance (3) (4)
EMIPA
Metal Production
Gold (oz) 13,000 -- 14,000
Copper (million lbs) 6.7 -- 7.5
Cash operating costs (co-product) ($/oz) gold (2)
(3) $1,900 - $2,300
Cash operating costs (co-product) ($/lb) copper $2.60 - $3.20
(2)
(3)
All-in sustaining costs (co-product) ($/oz) gold
(2)
(3) $2,200 - $2,600
All-in sustaining costs (co-product) ($/lb) $2.90 - $3.50
copper
(2) (3)
(2) Cash costs per ounce $(COC)$ and all-in sustaining costs
(AISC) per ounce are Non-GAAP Financial Performance
Measures, intended to provide additional information
to investors and do not have any standardized meaning
under International Financial Reporting Standards
("IFRS") as issued by the International Accounting
Standards Board, and therefore may not be comparable
to other issuers, and should not be considered in
isolation or as a substitute for measures of performance
prepared in accordance with IFRS. For further information,
please see the "Non-GAAP Financial Performance Measures"
section of the Company's Q1 FY2026 MD&A.
(3) COC and AISC are reported for gold and copper. Silver
production is accounted for as a by-product of gold,
and the associated revenues are credited against gold
production costs for the purpose of COC and AISC calculations.
EMIPA's fiscal 2026 guidance for COC and AISC assumes
an average BOB to U.S. Dollar exchange rate of 9.60.
EMIPA fiscal 2026 guidance for COC and AISC of gold
assumes a by-product silver price of $75 per ounce.
These assumptions are subject to change as operations
ramp-up.
(4) This guidance is based on the currently expected phased
restart of the Don Mario plant. Any significant deviations
from the planned restart schedule, changes in plant
operating performance, or variability in the mix of
oxide and legacy sulfide materials processed could
have a material impact on production assumptions,
grades, recoveries, and unit costs for the fiscal
year, including variability in the mix of stockpiled
materials processed and in the resulting grades. Cost
estimates are based on preliminary assumptions derived
from information currently available and may vary
as operations commence and stabilize, including during
commissioning and ramp-up, as well as due to changes
in operating consumptions, input prices, and other
cost drivers.
Argentina:
-- The current drilling program is designed to evaluate, for the first time,
the potential deep porphyry copper-gold system at the Taguas Property.
-- Ridgeback Geofísica Argentina S.A., an affiliate of Southernrock,
previously conducted MT and IP surveys over the southern portion of the
Taguas project, covering 4 km(2), between Cerro Campamento and Cerro
Cuarto (part of Cerros Taguas). The geophysical results identified a
north--south corridor of high chargeability and low resistivity,
consistent with potential sulfide mineralization and surface indicators
of porphyry copper (see news release dated January 28, 2026 for further
details). While not confirming an economic deposit, these data helped
define target areas for the drilling program.
-- Drilling commenced in January 2026 with a preliminary program of
approximately 4,500 metres using one drill rig, expected to be completed
by April 2026, subject to conditions and logistics. The drill rig has
started operations from the first platform, with the initial hole
targeting the core of the low-resistivity corridor between Cerro Taguas
Norte and Cerro Campamento. The planned depth for this hole is 1,500
metres, and as of the date of this press release, 356.5 metres have been
drilled, encountering 34 metres of morraine and ryolithic tuff after,
with some intervals of hidrotermal breccias(5).
(5) The scientific and technical information regarding
the Taguas Property in this news release has been
reviewed and approved by Raúl Álvarez Cifuentes,
EurGeol, a qualified person under NI 43-101 and an
(MORE TO FOLLOW) Dow Jones Newswires
February 11, 2026 19:30 ET (00:30 GMT)