Peninsula Energy Says Agitators At Wyoming Project Central Processing Plant Failed Due to Incorrect Installation
MT Newswires Live
Feb 19
Peninsula Energy (ASX:PEN) said as a result of incorrect installation by the contractor, both agitators at the Lance project central processing plant in Wyoming failed and require replacement, according to a Thursday Australian bourse filing.
During routine commissioning and ramp-up activities, installation-related deficiencies were identified in the agitator assemblies in both precipitation tanks.
Both agitator units were removed from service, and replacement kits were ordered from the manufacturer. Delivery is expected within five weeks to seven weeks.
Disclaimer: Investing carries risk. This is not financial advice. The above content should not be regarded as an offer, recommendation, or solicitation on acquiring or disposing of any financial products, any associated discussions, comments, or posts by author or other users should not be considered as such either. It is solely for general information purpose only, which does not consider your own investment objectives, financial situations or needs. TTM assumes no responsibility or warranty for the accuracy and completeness of the information, investors should do their own research and may seek professional advice before investing.