ACME Solar Commissions Second Phase of Bikaner BESS Project
MT Newswires Live
Mar 25
ACME Solar Holdings (NSE:ACMESOLAR, BOM:544283) said its subsidiary ACME Surya Power has commissioned the second phase of its battery energy storage system project in Bikaner, Rajasthan, according to a Tuesday filing on Indian bourses.
Shares of the company rose nearly 2% in Wednesday's trade.
The commissioned phase comprises 35.714 MW / 160.48 MWh, with commercial operations effective March 26, the filing said.
With this, the total commissioned capacity stands at 95.714 MW / 430.086 MWh out of the planned 250 MW / 1103.392 MWh project, the filing said.
Disclaimer: Investing carries risk. This is not financial advice. The above content should not be regarded as an offer, recommendation, or solicitation on acquiring or disposing of any financial products, any associated discussions, comments, or posts by author or other users should not be considered as such either. It is solely for general information purpose only, which does not consider your own investment objectives, financial situations or needs. TTM assumes no responsibility or warranty for the accuracy and completeness of the information, investors should do their own research and may seek professional advice before investing.