中国移动(广东汕头)数据中心二期项目备案于近日获批,总投资达4.97亿元人民币。该项目位于汕头市濠江区滨海街道南山湾产业园,将在二期部署机架和设备,建设IT总功耗45.4MW,折合标准机柜18,160架,计划从今年4月起开工至2028年12月1日完工。据悉,该中心一期2017年4月投产,已建成7,449个标准机架与3.2T出口带宽,构筑起粤东数字经济“核心底座”。(ta/w)AASTOCKS新闻
Source Link中国移动(广东汕头)数据中心二期项目备案于近日获批,总投资达4.97亿元人民币。该项目位于汕头市濠江区滨海街道南山湾产业园,将在二期部署机架和设备,建设IT总功耗45.4MW,折合标准机柜18,160架,计划从今年4月起开工至2028年12月1日完工。据悉,该中心一期2017年4月投产,已建成7,449个标准机架与3.2T出口带宽,构筑起粤东数字经济“核心底座”。(ta/w)AASTOCKS新闻
Source LinkDisclaimer: Investing carries risk. This is not financial advice. The above content should not be regarded as an offer, recommendation, or solicitation on acquiring or disposing of any financial products, any associated discussions, comments, or posts by author or other users should not be considered as such either. It is solely for general information purpose only, which does not consider your own investment objectives, financial situations or needs. TTM assumes no responsibility or warranty for the accuracy and completeness of the information, investors should do their own research and may seek professional advice before investing.