缺水缺电?消息称韩国1350万亿韩元半导体集群建设遇基建挑战

格隆汇
Jul 08

7月8日,科技媒体Tom's Hardware昨日发布博文,消息称在6月29日官宣为期10年的韩国产业投资计划,面临配套基础设施滞后问题,配套输电与供水存在较大挑战。

电力缺口方面,据韩国国会研究服务处报告显示,位于京畿道的龙仁半导体国家产业集群(三星和 SK 海力士的超级产业集群(全面运营时预计需要15至16吉瓦的电力,接近首尔都市圈总电力需求的25%,而当地电力供应量约为1.9吉瓦。

水资源方面,大型存储器制造厂每天耗水量超过10万吨,而龙仁国家级芯片制造厂全面建成后预计每天需要约80万吨水。根据韩国公告的阶段供水计划,从2031年左右开始,从八堂水坝的剩余水量和处理后的废水中供应约20万吨水;随后将新建取水设施和管道,到2034年达到每天60万吨的供水量。

美股频道更多独家策划、专家专栏,免费查阅>>

责任编辑:栎树

Disclaimer: Investing carries risk. This is not financial advice. The above content should not be regarded as an offer, recommendation, or solicitation on acquiring or disposing of any financial products, any associated discussions, comments, or posts by author or other users should not be considered as such either. It is solely for general information purpose only, which does not consider your own investment objectives, financial situations or needs. TTM assumes no responsibility or warranty for the accuracy and completeness of the information, investors should do their own research and may seek professional advice before investing.

Most Discussed

  1. 1
     
     
     
     
  2. 2
     
     
     
     
  3. 3
     
     
     
     
  4. 4
     
     
     
     
  5. 5
     
     
     
     
  6. 6
     
     
     
     
  7. 7
     
     
     
     
  8. 8
     
     
     
     
  9. 9
     
     
     
     
  10. 10