Toubani Resources Progresses Construction at Mali Gold Project; Shares Down 4%
MT Newswires Live
Aug 03
Toubani Resources (ASX:TRE) advanced its construction activities at the Kobada gold project in Mali, while an update to the project's mineral resource estimate is targeted to be completed during the September quarter, according to a Monday Australian bourse filing.
Bulk earthworks are progressing according to schedule, with the carbon-in-leach tank earthworks completed, the filing said. Construction of the water storage dam has been completed.
The fabrication and shipping of structural steel for the process plant is also progressing according to schedule, with over 500 tons fabricated to date and ball mill fabrication completed.
The company's shares fell nearly 4% in recent trading on Monday.
Disclaimer: Investing carries risk. This is not financial advice. The above content should not be regarded as an offer, recommendation, or solicitation on acquiring or disposing of any financial products, any associated discussions, comments, or posts by author or other users should not be considered as such either. It is solely for general information purpose only, which does not consider your own investment objectives, financial situations or needs. TTM assumes no responsibility or warranty for the accuracy and completeness of the information, investors should do their own research and may seek professional advice before investing.