Toubani Resources Says West Africa Project On Schedule for First Gold in Q3 2027; Shares Down 3%

MT Newswires Live
Oct 06

Toubani Resources (ASX:TRE) said the development of its Kobada Gold Project in West Africa remains on schedule for first gold in the third quarter of 2027, with construction of the carbon-in-leach tank now underway, according to a Tuesday Australian bourse filing.

Bulk earthworks are progressing at the tailings storage facility, and earthworks for the process plant are complete, the filing said.

Process plant engineering is more than 95% complete, with all long-lead mechanical items, including the ball mill, shipped, while a mineral resource estimate update is on track for October, Toubani said.

About $50 million from the company's $160 million stream facility has been drawn, and the proceeds have been received, the filing added.

The company's shares fell more than 3% in recent Tuesday trade.

Disclaimer: Investing carries risk. This is not financial advice. The above content should not be regarded as an offer, recommendation, or solicitation on acquiring or disposing of any financial products, any associated discussions, comments, or posts by author or other users should not be considered as such either. It is solely for general information purpose only, which does not consider your own investment objectives, financial situations or needs. TTM assumes no responsibility or warranty for the accuracy and completeness of the information, investors should do their own research and may seek professional advice before investing.